Last Updated | 04/17/2023 12:12 PM |
Project Title | Murphy USA #8667 / Fort Walton Beach |
Physical Address | View project details and contacts |
City, State (County) | Fort Walton Beach, FL 32548 (Okaloosa County) |
Category(s) | Commercial, Heavy and Highway |
Sub-Category(s) | Food/Beverage Service, Gas Station, Retail, Site Development, Vehicle Sales/Service |
Contracting Method | Bids by Invitation |
Project Status | Contract Award, Construction start expected May 2023 |
Bids Due | View project details and contacts |
Estimated Value | $2,500,000 [brand] Estimate |
Plans Available from | Owner |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Plans call for the construction of a gas station/convenience store. The project site is located on Beal Parkway & Mary Esther Cut Off. As of April 17, 2023, a general contract has been selected. There are currently 2 existing buildings on this site. The following scopes are needed, Fuel tank/system installation including canopy and dispensers, surveying, asbestos abatement, sitework including grease trap, sanitary sewer and water service, demolition, erosion control, earthwork, steel which consists of embeds for foundation and bollards, electrical ( including secondary & fuel system) plumbing, telephone, concrete paving , building & canopy foundations, landscaping & irrigation & dumpster enclosure (CMU and brick) New building is a modular structure that comes in sections furnished & installed by FMS - (Frey Moss Structures) and sets up on our foundation. All finishes are completed by FMS. Minor electrical and HVAC required, more for plumbing connections to underground water and sewer services. See items on plans that are marked by GC, other items marked by FMS are done by modular building contractor. See additional items on modular building that is noted as being done by GC's vendors as well as additional work by GC Direct all bids/inquiries to the GC bidders. Question PLAN C-6 FIRE HYDRENT NOT SHOWN ON PLAN NOTES SAY THERE IS ONE TO BE INSTALLED PLESAE CLARIFY Answer CPH; please provide irrigation plans ASAP for bid. By: John Goetz at 20-Mar-2023 05:16 AM CST Question IRRIGATION PLAN ISN'T IN THE PLAN ROOM PLEASE ADD Answer CPH please provide irrigation plan asap for bidding By: John Goetz at 20-Mar-2023 05:48 AM CST Revised utility & drainage plan has been issued as of 3-21-2023. The owner requests no email or phone inquiries. Addendum #1 has been issued as of 3-10-2023: Subject - soil & ground water management plan Addendum #2 - revised utility & drainage has been issued as of 3-21-2023. Addendum #3 - irrigation and bid notes as of 3-24-2023. |
||||||||||||||||||||||||||||||||||||||||||
Details | 1 Story Above Grade, 2,800 SF.
|
||||||||||||||||||||||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||
Project Documents |
![]() Engineered Spec Sheet ![]() Architectural Plans ![]() Other Documents |