Last Updated | 01/25/2023 11:03 PM |
Project Title | Hulston Hall - Replace Fire Alarm System |
Physical Address | View project details and contacts |
City, State (County) | Columbia, MO 65201 (Boone County) |
Category(s) | Single Trades |
Sub-Category(s) | Electric |
Contracting Method | Competitive Bids |
Project Status | Contract Award, Construction start expected February 2023 |
Bids Due | View project details and contacts |
Estimated Value | $272,750 [brand] Estimate |
Plans Available from | Electrical Engineer |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Information regarding bid results will be available the day following the bid opening by calling (573) 882-1133 A Diversity Participation goal of 10% Combined MBE, WBE, DBE, Veteran Owned Business and 3% SDVE has been established for this contract. The Owner reserves the right to waive informalities in bids and to reject any and all bids. Individuals with special needs as addressed by the Americans with Disabilities Act may contact (573) 882- 1133. Questions regarding the scope of work should be directed to Mark Jones with SSC Engineering at (636) 530- 7770 or mjones@sscengineering.com. Questions regarding commercial conditions should be directed to Scott Smith at (573) 882-9217 or smithws@missouri.edu. The Owner reserves the right to waive informalities in bids and to reject any and all bids. Individuals with special needs as addressed by the Americans with Disabilities Act may contact (573) 882- 1133 SCOPE OF WORK a. The Contractor shall furnish all labor, materials, tools, equipment necessary for, and incidental to, construction of this project as indicated on Drawings and specified herein. b. Work shall include everything requisite and necessary to finish work properly, notwithstanding that every item of labor or materials or accessories required to make project complete may not be specifically mentioned. c. General Description of Work: (1) Project consists of replacing the existing fire alarm system in its entirety. The existing system is a horn/strobe system and will be replaced with an Emergency Voice/Alarm Communication (EVAC) system. (2) Demolition shall consist of removing existing horn, horn strobes, strobes, duct detectors, smoke detectors, heat detectors, control and monitor modules, fire alarm power supplies, fire alarm control panel, wiring and all other appurtenances. (3) Provide and install new speakers, speaker/strobes, strobes, duct detectors, smoke detectors, heat detectors, control and monitor modules, fire alarm power supplies, fire alarm control panel, wiring and all other appurtenances for a complete system. (4) Electrical work shall consist of new wiring from existing panelboards to new fire alarm power supplies and reconnection to new fire alarm control panel. 4. LOCATION Work shall be performed under this Contract on campus of the University of Missouri - Columbia, at Hulston Hall located at the corner of Conley Ave. and Missouri Ave. CONSTRUCTION ESTIMATE: $300,265-$333,628 *The value for this project is based on a financial range. The value is listed as the highest possible cost from the range provided by a stakeholder or official project document. |
||
Details |
|
||
Bidder's List | View project details and contacts | ||
Prospective Bidders | View project details and contacts | ||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |