Project Title | SR 167 over Hop Bottom Creek |
Physical Address | View project details and contacts |
City, State (County) | Bridgewater Township, PA 18801 (Susquehanna County) |
Category(s) | Heavy and Highway |
Sub-Category(s) | Bridge, Paving/Reconstruction, Site Development |
Contracting Method | Bids by Invitation, Competitive Bids |
Project Status | Contract Award, Construction start expected March 2023 |
Bids Due | View project details and contacts |
Estimated Value | $2,374,064 [brand] Estimate |
Plans Available from | State Agency |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | As February 13, 2023, the project has been awarded. A timeline for construction has not been confirmed. For the improvement of a certain section of STATE ROUTE 0167, Sec 550 in Susquehanna COUNTY, Bridgewater TOWNSHIP. The location of the project is as follows: From a point approximately 1 mile North from the intersection with SR 3055 at Segment 0180 Offset 2847 (STA 942+90) in Brooklyn Township to a point approximatelymile South from the intersection with SR 2015 at Segment 0190 Offset 0473 (STA 952+38) in Bridgewater Township along SR 0167 (Brooklyn Road), with a total work area length of 848 feet (0.161 miles). The project consists of the replacement of the existing single span concrete T-beam bridge carrying SR 0167 over Hop Bottom Creek with a new single span composite concrete spread box beam bridge. The project will be staged construction maintaining a single lane controlled with a temporary traffic signal. Other work includes excavation, bridge approach roadway full depth reconstruction, Pile structure foundation, temporary excavation support & protection, drainage, new guiderail, bridge removal, existing bridge/ bridge beam repairs, E & S control measures, permanent signing, pavement markings, landscaping and other miscellaneous construction work. Project Cost Range: $1,000,000.00 - $2,499,999.99 Federal Project Status: PENNDOT Oversight Non-NHS Structure Work: 65.00% Pre-Bid Meeting: None Wage Rates: Yes Prequalification Requirement: Yes State Type of Work: BRIDGE REPLACEMENT 408 Version: 2020-5 PennDOT - SR 167 over Hop Bottom Creek *Project information has been obtained through a public state transportation improvement plan (STIP). A STIP is a financial schedule for short- and long-range projects which is updated regularly. Information listed in the STIP often evolves based on funding availability. The project details, including timeline and value, are subject to change. The content management team will continue to pursue additional details as they become available. sr/sec/ group id:167/550/--- *Information regarding subcontractor bidding has not been disclosed to the content management team at this time. Interested subcontractors should contact the general contractor directly for more information. |
||||||||||||||||||||
Details |
|
||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||
Project Documents |
![]() Engineered Spec Sheet ![]() Architectural Plans ![]() Other Documents |