Similar Projects
Last Updated | 02/03/2021 01:37 PM |
Project Title | Concrete Foundation for Substation 3 12KV Bus Split |
Physical Address | View project details and contacts |
City, State (County) | Saint Charles, IL (Kane County) |
Category(s) | Single Trades |
Sub-Category(s) | Concrete |
Contracting Method | Competitive Bids. |
Project Status | Results |
Bids Due | View project details and contacts |
Estimated Value | |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Contractor will construct eight (8) new 2'x12' concrete Pier foundations for structure supports and a total of seven (7) circuit breaker pads. ONLY hand excavation will be permitted in the substation. Contractor shall remove a minimum of 12 inches of material including the aggregate base course and place porous granular material underneath the "Pier" foundations, and compact it to ASTM Standard requirement. Contractor shall hand dig piers inside the energized substation area. |
||
Details |
|
||
Bidder's List | View project details and contacts | ||
Prospective Bidders | View project details and contacts | ||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |