Similar Projects
Last Updated | 04/20/2020 07:14 PM |
Project Title | SCADA System Improvements Phase III |
Physical Address | View project details and contacts |
City, State (County) | Salt Lake City, UT 84116 (Salt Lake County) |
Category(s) | Single Trades |
Sub-Category(s) | Security/Communications |
Contracting Method | Competitive Bids. |
Project Status | Results |
Bids Due | View project details and contacts |
Estimated Value | |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | The Work for this Project includes the following: 1. Construction of two new PLC back panels to replace existing PLC back panels in Switchgear #1 and Switchgear #2. 2. Construction of a new PLC panel to replace the existing PLC panel in the Influent Pump Station. 3. Demolition work associated with the removal of existing panels, conduit, wire boxes and concrete pads. 4. Electrical work in some locations to install new boxes, conduit and wire. 5. Electrical work in some locations to reroute existing conduit and replace existing wire. 6. Developing a cutover plan that minimizes outages and maximized safety. 7. Working with the Owner and the Owner’s System Integrator for the successful commissioning of a complete and operable system. |
||||
Details |
|
||||
Bidder's List | View project details and contacts | ||||
Prospective Bidders | View project details and contacts | ||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |