Project Title | RFP Design - Mckenzie Intake and Raw Water Pump Station |
Physical Address | View project details and contacts |
City, State (County) | Springfield, OR 97477 (Lane County) |
Category(s) | Professional Services |
Sub-Category(s) | Engineering |
Contracting Method | Competitive Bids |
Project Status | Construction start expected January 2025 , Request For Proposals |
Bids Due | View project details and contacts |
Estimated Value | $42,900,000 [brand] Estimate |
Plans Available from | Agency's Affiliate |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | SUB reserves the right to reject any and all proposals. Question Deadline 06/21/2023 at 4:00 PM PT The Class 4 construction cost estimate for Phase 1 of the conventional treatment facility is $26,700,000. The Class 4 construction cost estimate for Phase 2 is $9,700,000. For Phase 3, the Class 4 construction cost estimate is $6,500,000 if two new flocculation and sedimentation basins and two new filters are constructed. If the basins and filters constructed in Phase 1 and Phase 2 are uprated and no new basins are constructed, the Phase 3 construction cost estimate is reduced to $1,000,000. The total estimated build out construction cost in 2016 dollars for conventional treatment with six flocculation and sedimentation basins and eight filters is $42,900,000. The total estimated build out construction cost in 2016 dollars for conventional treatment with four flocculation and sedimentation basins and six filters is $37,400,000. |
||||||||||
Details |
|
||||||||||
Bidder's List | View project details and contacts | ||||||||||
Prospective Bidders | View project details and contacts | ||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |