Last Updated | 06/06/2023 07:04 PM |
Project Title | Chambers Street Paving |
Physical Address | View project details and contacts |
City, State (County) | Eugene, OR 97405 (Lane County) |
Category(s) | Single Trades |
Sub-Category(s) | Concrete |
Contracting Method | Competitive Bids |
Project Status | Contract Award, Construction start expected June 2023 |
Bids Due | View project details and contacts |
Estimated Value | $1,798,351 [brand] Estimate |
Plans Available from | Civil Engineer |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | **As of June 6, 2023, project was awarded to RiverBend Construction Co., awarded amount is $1,798,350.70.** Chambers Street Paving 900360 1 LS General Excavation; 1,810 LF 8-Inch Diameter Ductile Iron Pipe; 2,921 SY Aggregate Working Platform, 12" Thick; 70,950 SF Cold Plane Pavement Removal, 4 Inches Deep; 2,998 TN Level 3, 1/2 Inch ACP Mixture; 2,040 SF Concrete Walk, Ramp, 4 Inches Thick; 16 EA Detector Loop Installation; 1 LS Traffic Signal, Complete All work must be completed by September 1, 2023. A Bid guaranty is not required for this project. Filing of a qualification questionnaire before bidding will not be required. The City may reject any bid not in compliance with all prescribed public bidding procedures and requirements, and may reject for good cause any or all bids or to waive any specification or requirement upon a finding of the City that it is in the public interest to do so. For more information regarding this project, contact Jennah Maier at 541-852-2227 or jmaier@eugene-or.gov. Installing approximately 1810 feet of 8-inch ductile iron pipe and appurtenances, including maintaining temporary asphalt pavement along the project alignment per City of Eugene standards. Installing approximately 20 feet of 6-inch ductile iron pipe and appurtenances, including maintaining temporary asphalt pavement along the project alignment per City of Eugene standards Installing approximately (2) 2-inch services, including temporary and permanent restoration of the road surfacing per City of Eugene standards Installing approximately (42) 1-inch services, including temporary and permanent restoration of the road surfacing per City of Eugene standards. Installing (1) fire hydrants. Complete locate tracer wire continuity testing, water main flushing and hydrostatic pressure testing of the new pipeline. |
||
Details |
|
||
Bidder's List | View project details and contacts | ||
Prospective Bidders | View project details and contacts | ||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |