Similar Projects
Last Updated | 04/24/2023 04:04 AM |
Project Title | US 395 NSC Spokane River Crossing |
Physical Address | View project details and contacts |
City, State (County) | Spokane, WA 99201 (Spokane County) |
Category(s) | Heavy and Highway, Sewer and Water |
Sub-Category(s) | Bridge, Maintenance, Paving/Reconstruction, Site Development, Water Lines |
Contracting Method | Competitive Bids |
Project Status | Contract Award, Construction start expected June 2023 |
Bids Due | View project details and contacts |
Estimated Value | $68,633,025 [brand] Estimate |
Plans Available from | Civil Engineer |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Constructing two prestressed/post-tensioned concrete girder bridges, sign bridge, moment slab, pedestrian trail system, retaining walls, voided slab spans, steel bow truss bridge, path pier table landing, stairway and platform, earthwork, drainage, concrete and HMA paving, planting, guardrail, illumination, curbing, pavement markings, traffic control and other work. Involves 550 working days and 175 items. As of September 13, 2022, this project is in Final Planning status. Preliminary engineering has begun and environmental design is expected to be complete in the third quarter of 2022. The contract advertisement is expected in fourth quarter of 2022 and construction is anticipated to be operationally complete in the fourth quarter of 2025. Estimated value Over $50,000,000 A state funded project with a 5% condition of award small business enterprise goal and a 3% condition of award veteran owned business goal. WSDOT - US 395 NSC Spokane River Crossing Contract No- 000000 This Contract provides for the improvement of *** US 395, by constructing two prestressed/post-tensioned concrete girder bridges, sign bridge, moment slab, Pedestrian Trail System, retaining walls, voided slab spans, steel bow truss bridge, truss bridge, path pier table landing, stairway and platform, earthwork, drainage, concrete and HMA paving, planting, guardrail, illumination, traffic control, curbing, pavement markings *** and other work, all in accordance with the attached Contract Plans, these Contract Special Provisions, City of Spokane Special Provisions and Standard Plans, and the Standard Specifications . MBE (10%), WBE (6%), SBE (5%) This project shall be physically completed within *** 550 *** working days. |
||||||||||||||||||||||
Details |
|
||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |