Last Updated | 10/21/2021 03:16 PM |
Project Title | Vermilion East Pier Repair |
Physical Address | View project details and contacts |
City, State (County) | Vermilion, OH (Erie County) |
Category(s) | Heavy and Highway |
Sub-Category(s) | Dock/Pier/Marine |
Contracting Method | |
Project Status | Construction Commenced October 2020, Construction Nearing Completion, No Sub Bids Needed |
Bids Due | View project details and contacts |
Estimated Value | $1,000,000 to $2,000,000 |
Plans Available from | Federal Agency |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Repairs to the East section of the breakwall. At this time, there is not a linear feet estimate. This is NOT a request for proposal. Located on Lake Erie at the mouth of the Vermilion, Erie County,OH, Vermilion is a shallow draft recreational harbor with depths of 12 feet in the east lake approach channel, 12 feet in the entrance channel, 8 feet in the west lake approach channel, and 8 feet in the upper river channel. The east pier, west pier, and a detatched breakwater protect a total of 2,560 feet of the harbor. The |
||
Details |
|
||
Bidder's List | View project details and contacts | ||
Prospective Bidders | View project details and contacts | ||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |