Project Title | Old Stage Road Culvert Replacement and Paving |
Physical Address | View project details and contacts |
City, State (County) | Essex Jct, VT 05452 (Chittenden County) |
Category(s) | Heavy and Highway |
Sub-Category(s) | Maintenance, Paving/Reconstruction, Shoreline/Erosion/Drainage, Site Development |
Contracting Method | Competitive Bids |
Project Status | Construction start expected September 2022 |
Bids Due | View project details and contacts |
Estimated Value | $240,000 [brand] Estimate |
Plans Available from | Agency's Affiliate |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | The Town of Westford invites you to prepare a bid for the replacement of two culverts and repaving approximately 3,500 feet of Old Stage Road. All work shall conform to the engineering plans and the latest versions of Vermont Agency of Transportation Standard Specifications for Construction and the Town of Westford Town Road & Bridge Standards. 1. Replace existing culvert with one new (1) 36" HDPE culvert at station 7+24 (culvert to be provided by the Town). 2. Replace existing culvert with one new (1) 18" HDPE culvert at station 15+52 (culvert to be provided by the Town). 3. Mill existing asphalt and use the RAP as surface course. Regrade road surface. 4. Pave with 2 1/2 " type II base, 1 1/2 " type III top. 5. The Contractor shall supply all materials (except the two culverts), equipment, and labor in accordance with the engineering plan. 6. The Contractor shall contact DigSafe before work commences to ensure there are no buried utility lines. 7. The Contractor is required to provide all traffic control, construction warning signs, and associated barricades and traffic cones. 8. The Contractor shall submit with their bid a signed copy of the Town's Hold Harmless Agreement, and the Bidders Qualification form. Copies of each are provided within this bid package. The work shall occur between September 1, 2022 and September 30, 2023. No work shall be performed between October 31, 2022 and April 30, 2023. Preference is to have the two culverts installed before October 31, 2022 (to allow for settling before paving) and paving occurring between May 1, 2023 and September 30, 2023. |
||||||||||
Details |
|
||||||||||
Bidder's List | View project details and contacts | ||||||||||
Prospective Bidders | View project details and contacts | ||||||||||
Project Documents |
![]() Engineered Spec Sheet ![]() Architectural Plans ![]() Other Documents |