Similar Projects
Last Updated | 12/09/2022 07:33 AM |
Project Title | New Water Main on 2nd Ave, 2nd St. to 5th St. |
Physical Address | View project details and contacts |
City, State (County) | Hastings, NE 68901 (Adams County) |
Category(s) | Heavy and Highway, Sewer and Water |
Sub-Category(s) | Site Development, Water Lines |
Contracting Method | Competitive Bids |
Project Status | Contract Award, Construction start expected December 2022 |
Bids Due | View project details and contacts |
Estimated Value | $175,766 [brand] Estimate |
Plans Available from | Civil Engineer |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | New Water Main on 2nd Ave, from 2nd St. to 5th St Install new 8" water main via directional drilling. Each bid shall be accompanied by a certified check, drawn on a solvent bank in the State of Nebraska, or a bid bond in an amount of not less than five percent (5%) of the total bid of all contract construction costs, made payable to the City Treasurer of the City of Hastings, Nebraska, as security that the bidder to whom the contract may be awarded will enter into a contract to build all the improvements in accordance with this notice and give bond in the sum hereinafter provided for the construction of improvements. No bid shall be withdrawn after opening of bids without the consent of the City of Hastings, Nebraska, for a period of sixty (60) days after scheduled time of closing bids. Time is of the essence in this contract. In evaluating bid(s) received, the City will consider the timelines of completion of prior construction contracts, existing workload of bidders and available manpower that bidder commits to the project. The successful bidder will be required to furnish a Maintenance Bond in the sum of the full amount of the Contract within ten (10) days of the date of award. No additional time will be allowed the Contractor for providing the Maintenance Bond. General Questions or Requests-Renae Griess Engineering Admin Assistant Ph# 402-462-3665 Email: bidquestions@cityofhastings.org he Contractor shall provide all labor, equipment, materials, and appurtenances necessary to complete the work as described on the drawings. This contract is part of proposed work to be completed and therefore coordination between the projects must be executed. Contractor to identify all utility crossings along the proposed water main alignment. Contractor to provide a pipe installation plan profile which identifies all buried obstacles along with a bore plan and bore log. The intent of these contract documents, specifications, drawings, and appendix are to provide the Contractor a description of the proposed work. The following items of work will be furnished by the Owner or other Contractors: 1. Owner will perform soil compaction testing. |
||
Details |
|
||
Bidder's List | View project details and contacts | ||
Prospective Bidders | View project details and contacts | ||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |