Similar Projects
Last Updated | 06/20/2023 09:42 AM |
Project Title | Gotion Battery Component Manufacturing Facility |
Physical Address | View project details and contacts |
City, State (County) | Big Rapids, MI 49307 (Mecosta County) |
Category(s) | Heavy and Highway, Industrial/Manufacturing |
Sub-Category(s) | Industrial Warehouse, Site Development |
Contracting Method | Bids by Invitation |
Project Status | Conceptual Design, Construction start expected November 2023 |
Bids Due | View project details and contacts |
Estimated Value | $2,000,000,000 [brand] Estimate |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Plans include two 550,000 square foot production plants as well as an electrical substation, sewage treatment station, testing center, warehouse, and other supporting facilities. Location will be the Big Rapids Airport Industrial Park near Highway 131 and the Grand Rapids Airport. As of March 2023, the project is in the development/public comment phase. No plans have been submitted to the township for approvals to date. Public announcement was made regarding approvals of financial incentives for the project. Green Charter Township Board of Trustees will host a panel discussion April 5, 2023,concerning the project. Architect and General Contractor have not been selected. Construction timeframe is undetermined. |
||||||||||||||||||||||||||||||||
Details | 1,100,000 SF.
|
||||||||||||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |