Similar Projects
Pumping of Grease Traps and Catch Basins
Alteration
Post-Bid
River Falls, WI

Liquid Waste Pumping and Inspection Services
Alteration
Post-Bid
Madison, WI

2022 Sanitary Sewer Lining Mayer Street Area
Infrastructure
Results
$402,130 CJ est. value
Neenah, WI 54956

Welding Lab MEP Relocations for Equipment Connections
Alteration
Results
$200,000 est. value
Appleton, WI 54914

2022 Lead Service Line Replacement
Infrastructure
Construction
$581,013 CJ est. value
Hartford, WI 53027

Steam and Condensate Repairs
Renovation
Construction
$169,500 CJ est. value
Waupun, WI 53963

Water Heater Replacement and Miscellaneous Plumbing Repairs - Weatherization
Alteration
Post-Bid
$200,000 est. value
Milwaukee, WI

PSTC Propane Piping Replacement
Alteration
Results
$700,000 est. value
Appleton, WI 54914

Exterior Envelope Repair - Lathrop Hall and Van Vleck Hall
Renovation
Construction
$5,290,000 CJ est. value
Madison, WI 53706

Small Campground Cabins - Electrical, Plumbing and Concrete Work
Alteration
Post-Bid
$450,000 est. value
Hilbert, WI

Flood Resiliency Improvements at Jones Island Water Reclamation Facility
Renovation, Infrastructure
Results
$2,063,000 CJ est. value
Milwaukee, WI 53204

Fairgrounds Plumbing Lines Project
Alteration
Post-Bid
$700,000 est. value
Janesville, WI 53545

Jones Island Water Reclamation Facility, D and D Dry Vacuum System Rotary Valve Replacement
Renovation
Results
$60,000 CJ est. value
Milwaukee, WI 53207

Appleton Public Library - BU 22A Plumbing
New Construction, Infrastructure
Post-Bid
$200,000 CJ est. value
Appleton, WI 54911

GE Turbine Overhaul at Jones Island Water Reclamation Facility
Renovation
Results
$1,019,185 CJ est. value
Milwaukee, WI 53207

Last Updated 09/20/2023 01:36 PM
Project Title

300,000 Gallon Spheroid Exterior Overcoat Dry Interior Partial Repaint And Miscellaneous Repairs

Physical Address View project details and contacts
City, State (County) Fennimore, WI 53809   (Grant County)
Category(s) Single Trades
Sub-Category(s) Plumbing
Contracting Method Bids by Invitation, Competitive Bids
Project Status Bidding, Construction start expected April 2024
Bids Due View project details and contacts
Estimated Value $850,000 [brand] Estimate
Plans Available from Civil Engineer
Owner View project details and contacts
Architect View project details and contacts
Description

Tank Information: The Structure is a 300,000-gallon Spheroid Elevated Water Storage Tank With a Low-water Level of 109.7 Ft. Located at 1800 Street in Fennimore, Wisconsin. The Work Includes: Exterior: High Pressure Water Clean (5,000 to 10,000 Psi) and Spot Power Tool Clean to a Sspc-sp11 Standard. Apply a Three (3) Coat Epoxy Fluoropolymer System. Dry Interior: Abrasive Blast Clean the Entire Tops of the Platforms (Including 1 Ft. Up The Riser Wall), the Entire Bowl, and Spot Coating Failures Throughout to a Sspc-sp6 Commercial Standard. Apply a Three (3) Coat Epoxy System to the Bowl, a Two (2) Coat Epoxy System to the Platform Tops (and 1 Ft. Up the Riser Wall), and a Spot Two (2) Coat System to the Rest of the Prepared Surfaces. Pit Piping: Abrasive Blast Clean to a Sspc-sp6 Commercial Standard. Apply a Two (2) Coat Epoxy System. Foundation: Repair Grout. Water Clean and Apply a Two (2) Coat Epoxy System. Note L: the Engineer Assumes No Responsibility to Supply Builders Exchanges And Similar Plan Review Rooms With All Addenda Issued. An Attempt Will Be Made to Do So; However, Only Registered Plan Holders Will Be Notified by Email of Expected or Late Term Addendum With Short Preparation Times. Note 2: Prequalification of Bidders - Dixon Engineering Will Review Qualifications of All Contractors and Determine Their Status. Contractors Will Be Prequalified For Different Sized Tanks and Towers Based on Experience, Workmanship, Successful Project Completions With Dixon and Contractor's Financial Data. Prequalification Protocol is in the Instructions to Bidders. Any Contractor Who Has Any Projects in Dispute or Unfinished Because of Contract Problems Will Be Considered Not Prequalified. Disqualification Will Result in the Return of Any Handling Fee for Bidding Documents. Schedule and Liquidated Damages The Contractor is to Abide by the Following Schedule: The Contractor Has the Option to Perform the Work in the Spring or Fall of 2024 With the Following Schedules: Spring Schedule: Commence Work on or After April 15, 2024. Substantial Completion by May 27, 2024, Including Cure and Disinfection Time. The Tank May Be Out-of-service for a Maximum of 30 Days. Fall Schedule: Commence Work on or After September 18, 2024. Substantial Completion by October 27, 2024, Including Cure and Disinfection Time. Liquidated Damages Are Applicable and Begin After 30 Days Out-of-service or After Substantial Completion Date Whichever is the Earlier Date. Liquidated Damages at $1,250/calendar Day is to Apply After This Date. Ready for Final Payment Date is to Be Thirty (30) Days After Date Substantial Completion Date Based on Out-of-service Days or Scheduled Substantial Completion, or as Adjusted by Change Order, or Actual Substantial Completion if Earlier. Liquidated Damages After Ready for Final Payment Date of $250/day is to Apply. Liquidated Damages Are Cumulative if Damages From Substantial Completion and Ready for Final Payment Overlap. In Addition, Special Damages, Fines, or Set-off May Also Apply Per Bid/agreement Form. Mixer: Install a Mechanical Mixer. Repairs: 1) Replace the Wet Interior Roof Hatch. 2) Install a Handhold at the Access Tube Roof Hatch. 3) Install Ladder Extension at the Condensate Platform. 4) Install a Chemical Feed Tap on the Fill/draw Pipe. 5) Replace the Expansion Joint. 6) Install a Mud Valve. 7) Replace the Condensate Drain Line. 8) Overflow Discharge Modification. 9) Install a Fall Prevention Device on the Wet Interior Ladder. 10) Replace the Fall Prevention Devices on the Dry Interior Ladders. 11) Install an Additional Screen on the Roof Vent. 12) Install a Seal at the Access Tube Air Gap. 13) Install a Roof Painter's Railing. 14) Weld a Rigging Lug on the Bowl. 15) Relocate the Antenna Cable Penetrations. 16) Replace Light Fixtures in the Dry Interior 17) Replace the Aviation Light. 18) Replace the Dry Interior Light Bulbs. 19) Install an Aluminum Jacketing Over the Fill/draw Pipe Insulation. 1.02 Miscellaneous A. The Contractor is Responsible for Scheduling the Relocation of the Antenna Cables With the Antenna Owners. The Cables Will Need to Be Relocated When the New Penetrations Are Installed Through the Access Tube Cover Plate. Contact Information Will Be Given to the Contractor at the Preconstruction Meeting. B. Due to Supply Chain Issues, the Owner Reserves the Right to Require the Contractor to Have All of the Required Coating for the Project Delivered to the Site or to the Owner's Storage Facility Prior to the Tank Being Taken Out-of-service and Prior to the Commencement of the Project.

Details

Division 22 - Plumbing, Common Work Results for Plumbing.

Bidder's List View project details and contacts
Prospective Bidders View project details and contacts
Project Documents
 Engineered Spec Sheet
 Architectural Plans
 Other Documents