Similar Projects
Last Updated | 02/06/2023 11:35 PM |
Project Title | American Canal Lower Reach Replacement |
Physical Address | View project details and contacts |
City, State (County) | El Paso, TX 79901 (El Paso County) |
Category(s) | Heavy and Highway |
Sub-Category(s) | Dam/Tunnel, Shoreline/Erosion/Drainage, Site Development |
Contracting Method | Competitive Bids |
Project Status | Bidding, Request for Qualifications, Construction start expected April 2023 |
Bids Due | View project details and contacts |
Estimated Value | $10,000,000 [brand] Estimate |
Plans Available from | Civil Engineer |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | SS-4001 27341-000-01 PN_2022S4021001 IBM14C0009 Final written questions are due to the CO by December 30, 2022 (extension issued) at 2:00 pm MST. Submit questions in Microsoft Word file. The Contractor shall furnish all labor, material, and equipment necessary to complete American Canal Lower Reach Replacement. The solicitation is competed full and open. The resulting contract will be a firm fixed contract. In accordance with FAR provision 52.236-27 Alt 1, Site Visit (Construction) (Feb 1995), a site visit will be held Tuesday, November 29, 2022, at 9:00 AM MDT. All request for information must be submitted in writing (Microsoft Word Documents Only) no later than 2:00 PM MST on December 12, 2022. Questions shall be sent to Philip Johnson at philip.johnson@ibwc.gov. In Accordance with FAR Part 36.204 Disclosure of Magnitude of Construction projects the estimated magnitude of this project will be greater than $10,000,000.00. The applicable NAICS code is 237990, other Heavy Civil Construction. Offerors shall submit their proposals in accordance with the information reference in Subsection L.01, Proposal Instructions. Questions shall be submitted to arrive at the aforementioned address no later than 10:00 AM MDT on Monday, November 28, 2022 Small Business 42 % Small Disadvantage Business 5.0% Service-Disabled Veteran-Owned Small Business 3.0% Women Owned Small Business 5.0% HUBZone Small Business 3.0% The work for this project generally consists of removal and replacement of the Lower Reach of American Canal. 1.5.B. The major construction efforts include, but are not limited to, the following tasks: 1. Demolition of the existing canal lining 2. Demolition of temporary walls on College Arroyo Overchute structure 3. Removal of existing flume gates 4. Dewatering 5. Excavation and backfill 6. Placement of cast in place concrete 7. Installation of precast arch culverts 8. Construction of storm drops 9. Installation of handrails 10. Installation of landscape rock 11. Placement of topsoil 12. Revegetation by seeding 13. Establishment and maintenance of revegetation 14. Coordination with EPWater for relocation of the Upper Valley Outfall and demolition of the existing Upper Valley Outfall abutments after EPWater relocates the sewer line |
||||||||
Details |
|
||||||||
Bidder's List | View project details and contacts | ||||||||
Prospective Bidders | View project details and contacts | ||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |