Similar Projects
Last Updated | 10/03/2023 10:07 AM |
Project Title | Wastewater Treatment Plant Transfer Pumps Improvements Project |
Physical Address | View project details and contacts |
City, State (County) | San Mateo, CA 94404 (San Mateo County) |
Category(s) | Single Trades |
Sub-Category(s) | Plumbing |
Contracting Method | Competitive Bids |
Project Status | Bidding, Construction start expected November 2023 |
Bids Due | View project details and contacts |
Estimated Value | $512,750 [brand] Estimate |
Plans Available from | Copy Center |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | **As of August 31, 2023, bids were rejected. No definite date for the rebid.** Transfer Pumps Improvements Project The estimated construction cost of this Package is $365,600. All Bids shall be accompanied by a Bid bond, cashier's check, or certified check made payable to the City of San Mateo in an amount not less than ten percent (10%) of the aggregate amount of the Bid. The time of substantial completion for this Contract shall be 140 working days, beginning from the date. The right is reserved, as the interest of the City may require, to reject any or all Bids, to waive any informality in Bids, and to accept, modify, or reject any items of the Bid, or in the case of a single Bid being received to extend the acceptance date by up to thirty (30) days with notice. The City of San Mateo is a charter City and any Contract entered into is subject to the provisions of the City of San Mateo Charter, which may supersede certain provisions of the Public Contract Code and other provision of state law. To ensure performance, City reserves the right to retain five percent (5%) of the Contract price for 35 days after it records the Notice of Completion. However, pursuant to the Public Contracts Code Section 22300, Contractor may substitute securities for said five percent (5%) retention or request that City make payments of retentions earned directly to an escrow agent at Contractor's expense. The provisions of the Public Contracts Code Section 22300 are hereby expressly made a part of the Contract. Any questions regarding the Contract Documents should be directed to Deryk Daquigan, Project Manager, in writing to ddaquigan@cityofsanmateo.org. |
||
Details |
|
||
Bidder's List | View project details and contacts | ||
Prospective Bidders | View project details and contacts | ||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |