Last Updated | 01/09/2023 09:03 AM |
Project Title | Geisinger Grays Woods |
Physical Address | View project details and contacts |
City, State (County) | Port Matilda, PA 16870 (Centre County) |
Category(s) | Heavy and Highway, Medical |
Sub-Category(s) | Hospital, Site Development |
Contracting Method | Bids by Invitation |
Project Status | Contract Award, Construction start expected April 2023 |
Bids Due | View project details and contacts |
Estimated Value | $3,000,000 [brand] Estimate |
Plans Available from | General Contractor |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | As of January 9, 2023, a general contractor has been awarded. The project is moving forward likely starting at the break of spring pending land development approvals. LDs will be approved, but the process may extend into late spring. Poole Anderson will be conducting a turnover meeting at which time the PM, Phil Weller, will begin reaching out for final discussions, contracting, and select material procurement. New, two-story addition to the Geisinger Grays Woods facility. Scope includes significant utility relocations, site demo/excavation/paving, concrete foundations, structural steel/decking, EPDM roofing, framing, wall/ceiling/floor finishes, and MEP/FP systems. The new addition will tie into the existing building with minor renovations to those connection points. Select MEP systems will feed from the existing facility plant. - Project will be handled during regular business hours with the exception of disruptive tie-in / shut down work. - Project is non prevailing wage rates. *Vaccination Mandates Vaccination policy from Geisinger which is as follows: - All workers entering the Geisinger property will require either the COVID vaccination OR exemption to the vaccination. - Vaccination / Exemption documentation should remain with respective employers and should NOT be sent to Poole Anderson or Geisinger. A direct line of communication between Geisinger's medical safety supervisor may occur if proof is requested. - Masking will be required when working within the existing facility or within the enclosed building addition. - Masking will not be required when outdoors such as site work, concrete, steel framing, roofing, exterior facades, etc. prior to the addition being enclosed. *Addendum 01, 02 and 03 have been released. *RFI Responses have been released. |
||||||||||||||||||||||||||||||||||||||||||||||
Details | 2 Stories Above Grade, 24,395 SF.
|
||||||||||||||||||||||||||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |