Reported | 10/23/2020 12:00 AM |
Project Title | WWTP Improvements Phase 2A - Sludge Processing Improvements and Phase 2B - New Sludge Processing Building |
Physical Address | View project details and contacts |
City, State (County) | Bristol, IN (Elkhart County) |
Category(s) | Sewer and Water |
Sub-Category(s) | Sewage Treatment Plant |
Contracting Method | Competitive Bids. |
Project Status | Bidding |
Bids Due | View project details and contacts |
Estimated Value | |
Plans Available from | Engineer |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | The Project consists of constructing the following: WWTP Improvements Phase 2A - Sludge Processing Improvements The project includes but is not limited to removal and disposal of all sludge in the existing sludge holding tank, new sludge pump and controls, new sludge bag dewatering system, and all other work required for the complete sludge processing improvements as defined in the plans and specifications. WWTP Improvements Phase 2B - New Sludge Processing Building The project includes but is not limited to construction of a new pre-engineered building over the existing sludge bag dewatering facilities, electrical and HVAC system, and all other work required to make the building operational and as defined in the plans and specifications. |
||||||||||||||||||||||||||||||||||||||||||
Details |
|
||||||||||||||||||||||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |