Last Updated | 04/11/2023 03:20 PM |
Project Title | UCOR Alpha-2 Utility Bridge at Y-12 NSC |
Physical Address | View project details and contacts |
City, State (County) | Oak Ridge, TN 37830 (Anderson County) |
Category(s) | Heavy and Highway |
Sub-Category(s) | Maintenance, Site Development |
Contracting Method | Bids by Invitation |
Project Status | Bidding, Construction start expected May 2023 |
Bids Due | View project details and contacts |
Estimated Value | $5,000,000 [brand] Estimate |
Plans Available from | Selected Bidders |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Project Description - Traffic control plan for Second Street closure - Over-the-road utility bridges and foundations (1 permanent bridge on the East end of the project and 2 temporary bridges on the West end on the project) - Restoration of areas disturbed during the work All labor, material, equipment, tools, and services required to execute this project are included in the scope, except those specified to be furnished or performed by the CONTRACTOR. The work scope includes, but is not limited to, fabrication, procurement and installation of the commodities/items listed below - Refer to the Issued for Construction (IFC) design engineering package for specific details. But not limited to please review the specifications for more information. Magnitude of Construction: $2M - $5M *Amendment 1, 2 and 3 have been released. |
||||
Details |
|
||||
Bidder's List | View project details and contacts | ||||
Prospective Bidders | View project details and contacts | ||||
Project Documents |
![]() Engineered Spec Sheet ![]() Architectural Plans ![]() Other Documents |