Similar Projects
Reported | 02/11/2022 12:00 AM |
Project Title | BIA Pressure Zone Infrastructure Expansion - Water Main Replacement |
Physical Address | View project details and contacts |
City, State (County) | Bangor, ME (Penobscot County) |
Category(s) | Sewer and Water |
Sub-Category(s) | Water Lines |
Contracting Method | Competitive Bids. |
Project Status | Bidding |
Bids Due | View project details and contacts |
Estimated Value | |
Plans Available from | Engineer |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | The installation of approximately 2,000 feet of new 12-inch ductile iron water main on Corporate Drive and 900 feet of new 12-inch ductile iron main on Venture Way; the replacement of approximately 2,000 feet of existing 10-inch cast iron water main on Maine Avenue with 16-inch ductile iron water main, the replacement of approximately 3,100 feet of existing 12 and 8-inch cast iron water main on Hildreth Street, and the replacement of approximately 600 feet of 16-inch ductile iron on Venture Way. The new mains will be 12 and 16-inch ductile iron pipe, along with associated valves, interconnections, and hydrants. The Contractor shall furnish and install the water main pipe and fittings and all associated appurtenances including hydrant assemblies, valves, valve and service boxes, brass wedges, and pipe adapters. |
||
Details |
|
||
Bidder's List | View project details and contacts | ||
Prospective Bidders | View project details and contacts | ||
Project Documents |
![]() Engineered Spec Sheet ![]() Architectural Plans ![]() Other Documents |