Reported 04/01/2022 12:00 AM
Project Title

2022 Sinking Fund Projects - Flooring

Physical Address View project details and contacts
City, State (County) Garden, MI 49835   (Delta County)
Category(s) Single Trades
Sub-Category(s) Flooring
Contracting Method Competitive Bids.
Project Status Bidding, Construction Start Expected May 2022
Bids Due View project details and contacts
Estimated Value
Plans Available from Architect
Owner View project details and contacts
Architect View project details and contacts
Description

Removal of existing hard floor tile and base. Installation of new luxury vinyl tile and base. Approximate work area 9,830 square feet. The structure is a 1,000,000 gallon radial arm water storage tank (Roberts Tank) with an estimated highwater level of 120 ft. located at 712 Roberts St. in Muskegon, Michigan. Exterior: High pressure water clean (5,000 to 10,000 psi), spot power tool clean to a SSPC-SP11 standard and apply a three (3) coat epoxy urethane system. Wet Interior: Spot abrasive blast clean the coating failures to a SSPC-SP10 near-white metal standard and apply a two (2) coat epoxy system. Dry Interior: Abrasive blast clean the entire access leg interior and access tube interior to a SSPC-SP6 commercial standard and apply a three (3) coat epoxy system. Foundation: Remove shrubs adjacent to foundation. Repair spalls. Water clean and apply a two (2) coat epoxy system. Mixer: Install a mechanical mixer. Repairs: 1) Replace the riser manway gaskets. 2) Install a gasket on the wet interior roof hatch. 3) Install a hasp on the wet interior roof hatch. 4) Install a handhold at the wet interior roof hatch. 5) Overflow discharge modification. 6) Adjust fall prevention device on the dry interior access tube and wet interior ladders. 7) Install bowl rigging couplings. 8) Install painter’s railing stand-offs. 9) Patch plate on the wet interior platform 10) Weld a plate around the overflow penetration at the bottom of the access tube. 11) Access leg drain holes. 12) Replace light fixtures. 13) Electrical conduit repair. 14) Change all light bulbs in the dry interior.

Details

Division 09 - Finishes, Flooring.

Bidder's List View project details and contacts
Prospective Bidders View project details and contacts
Project Documents
 Engineered Spec Sheet
 Architectural Plans
 Other Documents