Similar Projects
Last Updated | 04/07/2023 12:07 PM |
Project Title | Library Condensation Mitigation |
Physical Address | View project details and contacts |
City, State (County) | Kapolei, HI 96707 (Honolulu County) |
Category(s) | Education, Government/Public |
Sub-Category(s) | Elementary School, Library - Public |
Contracting Method | Competitive Bids |
Project Status | Construction start expected December 2022 , Construction documents |
Bids Due | View project details and contacts |
Estimated Value | $2,969,060 [brand] Estimate |
Plans Available from | Agency's Affiliate |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | "As per the Owner the project has been cancelled. Editorial Content Team is actively seeking updated information” Per Section 103D-308, HRS the University of Hawaii is cancelling this solicitation due to insufficient funds to award the project. Project was initially advertised on 2/1/22 with bids due on 3/22/22 10 Business day cancellation notice as required by Section 103D-308, HRS. T.M.K.: 9-1-016:220 UHWO Library Condensation Mitigation to include firestopping, access doors and panels, gypsum board, acoustical ceiling, painting, coating, special construction, mechanical, and electrical work. Questions Deadline: The deadline to submit requests for clarification of the requirements of this IFB is 4:00 p.m. (HST) on March 11, 2022.. All clarification requests shall be submitted via HePS QUESTIONS AND ANSWERS section (HEPS (SICOMM.NET), and all responses shall be issued in an addendum. The project shall generally consist of, but is not limited to, the renovation of the existing HVAC system; repairs to the DDC/RxC; adjustments to AHU3-1, PCC 3-1, AHU 3-2, PCC 3-2, CHWP 3-1, VAVs, fan coil units and exhaust fans; selective demolition, removal and replacement of failing insulation; removal, patching, repair and installation of drywall ceiling as required; duct liner repair; duct cleaning; duct insulation installation; CHW pipe insulation installation; exhaust fan installation; HVAC equipment sensor installation; painting; containment for construction phasing; environmental monitoring (which includes mold hazard control, testing/air monitoring, and silica exposure control); final TAB, and incidental work as called for in the Plans and Technical Specifications. The deadline to submit requests for clarification of the requirements of this IFB is 4:00 p.m. (HST) on March 11, 2022. |
||||||||||||||||||||||||||||||||||||||||||
Details |
|
||||||||||||||||||||||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |