Last Updated | 07/07/2023 09:03 AM |
Project Title | WWTP Vertical Loop Reactor Replacement Air Piping |
Physical Address | View project details and contacts |
City, State (County) | Carroll, IA 51401 (Carroll County) |
Category(s) | Single Trades |
Sub-Category(s) | Plumbing |
Contracting Method | Competitive Bids |
Project Status | Construction start expected July 2023 , Construction documents |
Bids Due | View project details and contacts |
Estimated Value | $390,000 [brand] Estimate |
Plans Available from | Civil Engineer |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Over budget, no award being made per city Engineer and Engineers project number (27362) Work is located at the Wastewater Treatment Plant, Carroll, Iowa Construct WWTP Vertical Loop Reactor Replacement Air Piping including all labor, equipment, and materials necessary for excavation, backfill and sitework, sheeting, shoring and bracing, reinforced concrete footings, piping and appurtenances, and miscellaneous associated work, including cleanup. Also, at 5:15 P.M. on the 28 th day of November, 2022, the City Council of said City will, in said Council Chambers at 627 N. Adams Street, or at such time, date and place as then may be fixed, to act upon proposals and enter into a contract for the construction of said improvements. Each bid shall be made out on a blank form furnished by the City and must be accompanied by bid security, as follows: a certified or cashier's check, drawn on a solvent Iowa bank or a bank chartered under the laws of the United States or a certified share draft drawn on a credit union in Iowa or chartered under the laws of the United States, in an amount equal to five percent (5%) of the bid, or a bid bond executed by a corporation authorized to contract as a surety in the State of Iowa in a penal sum of five percent (5%) of the bid. Liquated damages in the amount of Two Hundred Fifty Dollars ($250.00) per consecutive calendar day will be assessed for each day that the Vertical Loop Reactor is not in full operation treating wastewater after October 17, 2023 with due allowance for extensions due to conditions beyond the control of the contractor. As of July 7, 2023, no new information available |
||
Details |
|
||
Bidder's List | View project details and contacts | ||
Prospective Bidders | View project details and contacts | ||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |