Last Updated | 10/16/2023 07:34 AM |
Project Title | Regional Water System Phase 2 Pipeline Improvements - 2024 |
Physical Address | View project details and contacts |
City, State (County) | Hermiston, OR 97838 (Umatilla County) |
Category(s) | Heavy and Highway, Sewer and Water |
Sub-Category(s) | Maintenance, Site Development, Water Lines |
Contracting Method | Competitive Bids |
Project Status | Bidding, Construction start expected December 2023 |
Bids Due | View project details and contacts |
Estimated Value | $8,500,000 [brand] Estimate |
Plans Available from | Civil Engineer |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | The Work for this Project includes, but is not limited to, the installation of approximately 13,750 linear feet (LF) of 30-inch ductile iron water pipe with two separate jack and bore railroad crossings and a canal crossing, an additive alternate for 8,500 LF of 18-inch polyvinyl chloride industrial wastewater line and 2,250 LF of 8-inch pressure sewer line with two separate jack and bore railroad crossings, and 12,000 square yards of surface restoration. A pre-bid conference will not be held for this Project. The Project has an expected duration of 270 days. Est. Value Notes:Base Bid - $8,000,000 to $8,500,000; Additive Alternative - $3,000,000 to $3,500,000 Owner on its own initiative may issue Addenda to clarify, correct, supplement, or change the Bidding Documents.Question Deadline 10/17/2023 7.02 Bidder shall submit all questions about the meaning or intent of the Bidding Documents to Engineer in writing. 7.03 Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda delivered to all registered plan holders. Questions received less than seven days prior to the date for opening of Bids may not be answered. *The value for this project is based on a financial range. The value is listed as the highest possible cost from the range provided by a stakeholder or official project document. Bidder shall submit all questions about the meaning or intent of the Bidding Documents to Engineer in writing. |
||||||
Details |
|
||||||
Bidder's List | View project details and contacts | ||||||
Prospective Bidders | View project details and contacts | ||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |