Project Title | Epitome Energy Soybean Processing Plant / Biodiesel Facility |
Physical Address | View project details and contacts |
City, State (County) | Crookston, MN 56716 (Polk County) |
Category(s) | Heavy and Highway, Industrial/Manufacturing |
Sub-Category(s) | Manufacturing/Processing Plant, Site Development |
Contracting Method | Bids by Invitation |
Project Status | Design Development, Construction start expected August 2023 |
Bids Due | View project details and contacts |
Estimated Value | $130,000,000 [brand] Estimate |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | The scope of this project includes, but is not limited to, the following: site work and new construction of an industrial development. As of July 11, 2023, this project is in pre-con/negotiated. The Crookston City Council recently approved a $250,000 loan to assist in the project and are expected to request anywhere from $7 to $9 million in the form of state bonding dollars to cover infrastructure costs associated with the Epitome Energy project. A general contractor has been assigned, but information regarding the architect has not yet been released. While a firm construction timeline has not yet been established, construction is expected to begin in Summer 2023. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||
Details |
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |