Similar Projects
Last Updated | 03/29/2023 01:04 AM |
Project Title | NE Columbia Boulevard: Cully Boulevard and Alderwood Road |
Physical Address | View project details and contacts |
City, State (County) | Portland, OR 97218 (Multnomah County) |
Category(s) | Heavy and Highway |
Sub-Category(s) | Maintenance, Paving/Reconstruction, Sidewalks/Parking Lot, Site Development |
Contracting Method | Competitive Bids |
Project Status | Construction start expected June 2024 , Construction documents |
Bids Due | View project details and contacts |
Estimated Value | $5,331,069 [brand] Estimate |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | UPDATE : https://www.portlandoregon.gov/cbo/article/785597 This project will construct a traffic signal at the intersection of NE Alderwood Rd and NE Columbia Blvd. The project will also include evaluation and preliminary design of a paired traffic signal at NE Cully Blvd. The project is a joint project with the Port of Portland. Construction is planned for 2019. The project will be negotiating ROW in 2021 and start construction in summer of 2022. Project is included City of Portland FY 2021 - 2022 CIP Page 341. ---------------------------------------------------------------------------------------------------------------------------------- www.portlandoregon.gov/cbo/article/764228 This project will construct a traffic signal at the intersection of NE Alderwood Rd and NE Columbia Blvd. The project will also include evaluation and preliminary design of a paired traffic signal at NE Cully Blvd. The project is a joint project with the Port of Portland. Construction is planned for 2019. Project is included City of Portland FY 2020-2024 CIP Page 327 _________________________________________________________________________________________________________________________________ Install or replace a signal and construct a taper on Columbia Blvd's east leg at Alderwood for future side-by-side left-turn lanes between Cully and Alderwood. Construct sidewalks at the Columbia/Alderwood intersection and on N side to Cully. As of March 29, 2023, the project is in Final Planning planning status. Anticipated letting year 2024. ODOT - NE Columbia Boulevard: Cully Boulevard and Alderwood Road *Project information has been obtained through a public state transportation improvement plan (STIP). A STIP is a financial schedule for short- and long-range projects which is updated regularly. Information listed in the STIP often evolves based on funding availability. The project details, including timeline and value, are subject to change. The content management team will continue to pursue additional details as they become available. |
||||||
Details |
|
||||||
Bidder's List | View project details and contacts | ||||||
Prospective Bidders | View project details and contacts | ||||||
Project Documents |
![]() Engineered Spec Sheet ![]() Architectural Plans ![]() Other Documents |