Similar Projects
Last Updated | 06/23/2022 03:25 AM |
Project Title | SouthWest Makah Court to Saum Creek Storm Line Repair |
Physical Address | View project details and contacts |
City, State (County) | Tualatin, OR 97062 (Washington County) |
Category(s) | Heavy and Highway, Sewer and Water |
Sub-Category(s) | Landscaping, Shoreline/Erosion/Drainage, Storm/Sewers |
Contracting Method | Competitive Bids. |
Project Status | Results |
Bids Due | View project details and contacts |
Estimated Value | $120,000 to $200,000 |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | IDENTIFICATION OF PROJECT: Major items of work consist of the following: underground pipe bursting, storm sewer utility replacement, repair of existing catch basin, slope stabilization utilizing the Envirolok geobag system, in-water work, vegetated corridor enhancements, landscaping, erosion control, and other items as called for on the plans. CONTRACT TIME: The Contractor shall begin construction work within 40 calendar days following the Notice to Proceed and no sooner than the start of the in-water work window of July 15, 2022. The contractor shall reach final completion of the project (including all punch list items) no later than September 30, 2022 in compliance with the Oregon Guidelines for Timing of In-Water Work to Protect Fish and Wildlife Resources. OTHER BID REQUIREMENTS: No proposal for a construction contract shall be received or considered by the City unless the firm is registered with the Construction Contractors Board or is licensed by the State Landscape Contractors Board, as applicable, as specified in OAR 137- 049-0230. Proposals must be made upon the Proposal form bound in the Contract Documents and must be accompanied by a certified check or proposal bond payable to the City of Tualatin (County of Washington, State of Oregon) in an amount not less than ten percent (10%) of the total amount of the bid. Every subcontract must contain a provision requiring payment of prevailing wage pursuant to the provisions of ORS 279C.800 through 279C.870. Contractor and all subcontractors must file or cause to be filed the certified statements with the BOLI, as provided in ORS 279C.845. The bid must indicate whether the contractor is a resident contractor, as defined in ORS 279A.120. RIGHT OF REJECTION: The City of Tualatin reserves the right to reject any bid not in compliance with all prescribed public procedures and requirements and may reject for good cause any or all bids upon a finding that it is in the public interest to do so. Bids cannot be withdrawn within thirty days (30) after the Bid Closing. WRITTEN ADDENDA: The City reserves the right to make changes to the Invitation to Bid and the Contract Documents by written addenda prior to the Bid Closing. Addenda shall be made available to all contractors who have joined the plan holders list on the City of Tualatin bid website, as provided in the Contract Documents. ENGINEER'S ESTIMATE: $120,000 TO $200,000 |
||||||||||
Details |
|
||||||||||
Bidder's List | View project details and contacts | ||||||||||
Prospective Bidders | View project details and contacts | ||||||||||
Project Documents |
![]() Engineered Spec Sheet ![]() Architectural Plans ![]() Other Documents |