Last Updated | 04/26/2023 04:13 PM |
Project Title | Spring Valley CID No. 1 - Waste Water Treatment Plant Phase I |
Physical Address | View project details and contacts |
City, State (County) | Eagle, ID 83616 (Ada County) |
Category(s) | Single Trades |
Sub-Category(s) | Concrete |
Contracting Method | Competitive Bids |
Project Status | Contract Award, Construction start expected October 2022 |
Bids Due | View project details and contacts |
Estimated Value | $17,087,277 [brand] Estimate |
Plans Available from | Architect |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Project Category Code: Site work/Excavating and Grading, Electrical and Controls, Plumbing, Water and Wastewater Facilities, Heating, Ventilation, Air Conditioning (HVAC) Description: The Project generally consists of constructing a screen building, an influent pump station, aerated lagoon cells, weir structures, settling ponds, chlorine mixing structures, manholes, flow metering structures, winter storage ponds, a chemical building, an irrigation pump station, electrical, controls, plumbing, HVAC, site work, yard piping, and other items of miscellaneous work as shown on the drawings and described in the specifications. Additional Description: The Owner has entered into contracts for the pre purchase of an air gap system, emergency generators, vertical turbine pumps, lift station pumps and controls, lagoon liner system, a grinder pump station, a vertical manhole screen, surface aerators, piping and valves. The Owner will assign these contracts to the selected bidder. The contract value and contract holder for this equipment is listed in the bid schedule. Liquidated damages : Contractor shall pay Owner $_1,500_ for each day |
||
Details |
|
||