Last Updated | 08/12/2022 05:01 AM |
Project Title | 2022 Thin Bituminous Overlay/City Hall Parking Lot Improvements Project |
Physical Address | View project details and contacts |
City, State (County) | Centerville, MN 55038 (Washington County) |
Category(s) | Heavy and Highway |
Sub-Category(s) | Paving/Reconstruction, Sidewalks/Parking Lot, Site Development |
Contracting Method | Competitive Bids |
Project Status | Construction start expected September 2022 |
Bids Due | View project details and contacts |
Estimated Value | $50,000 [brand] Estimate |
Plans Available from | Civil Engineer |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | neighborhood. Also included is the replacement of bituminous pavement at the City Hall parking lot. The Project consists of the following approximate quantities: 40,000 SQ YD Bituminous Milling (1") 110 EACH Structure Adjustment 1,400 LIN FT Remove and Replace Concrete Curb and Gutter 400 CY Select Granular Borrow 550 TON Class 5 Aggregate Base 3,000 TON Bituminous Paving Materials 450 CY Common Excavation 1,100 LF Parking lot striping 500 SQ YD Restoration Along with miscellaneous utility improvements, removals, erosion control, restoration, and correlated appurtenances. The Owner reserves the right to retain the deposits of the 3 lowest Bidders for a period not to exceed 60 days after the date and time set for the Opening of Bids. No Bids may be withdrawn for a period of 60 days after the date and time set for the Opening of Bids. The Owner reserves the right to reject any and all Bids, to waive irregularities and informalities therein, and further reserves the right to award the Contract to the best interests of the Owner. The successful bidder must be a "responsible contractor." The term "responsible contractor" means a contractor as defined in Minnesota Statutes, section 16C.285, subdivision 3. Any prime contractor, subcontractor, or motor carrier that does not meet the minimum criteria or fails to comply with the verification requirements is not a responsible contractor and is not eligible to be awarded a construction contract for the project or to perform work on the project. A prime contractor, subcontractor, or motor carrier that makes a false statement under oath verifying compliance with the minimum criteria will be ineligible to be awarded a construction contract on the project, and the submission of a false statement may result in termination of a contract awarded to a prime contractor, subcontractor, or motor carrier that submits the false statement. A prime contractor shall include in its verification of compliance a list of all of its first-tier subcontractors that it intends to retain for work on the project. Before execution of a construction contract, a prime contractor shall submit a supplemental verification under oath confirming that all subcontractors and motor carriers that the prime contractor intends to use to perform project work have verified to the prime contractor, through a signed statement under oath by an owner or officer, that they meet the minimum criteria for a responsible contractor. Mark Stats Administrator City of Centerville, Minnesota. |
||||||||
Details |
|
||||||||
Bidder's List | View project details and contacts | ||||||||
Prospective Bidders | View project details and contacts | ||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |