Similar Projects
Last Updated | 11/18/2022 09:03 PM |
Project Title | Wyboo Plantation Wastewater Treatment Plant Wastewater Flow Diversion Pump Station and Force Main to the City of Manning Wastewater Treatment Facility |
Physical Address | View project details and contacts |
City, State (County) | Columbia, SC 29201 (Richland County) |
Category(s) | Heavy and Highway, Sewer and Water |
Sub-Category(s) | Lift and Pump Stations, Sewage Treatment Plant, Site Development, Water Lines |
Contracting Method | Competitive Bids |
Project Status | Contract Award, Construction start expected November 2022 |
Bids Due | View project details and contacts |
Estimated Value | $2,432,676 [brand] Estimate |
Plans Available from | Consultant |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | **As of November 18, 2022, project was awarded to Barwick Plumbing, awarded amount is $2,432,675.60.** Construction of a new 180-GPM Pump Station, including a receiving manhole, upgrades to the existing Pump Station, Flow Reversal of the existing Force Main, and construction of the new Force Main. Specific details are included within the Construction Plans and Technical Specifications. Project Location: Clarendon County managed by Alliance Consulting Engineers, Inc., Post Office Box 8147, Columbia, South Carolina 29202 |
||||||||||||||||||||||||||||||||||||||||||||||||||
Details |
|
||||||||||||||||||||||||||||||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |