Last Updated | 09/19/2023 10:18 AM |
Project Title | SE Archer Avenue Extension SE Laurel Street to E Hickman Road |
Physical Address | View project details and contacts |
City, State (County) | Waukee, IA 50263 (Dallas County) |
Category(s) | Heavy and Highway, Sewer and Water |
Sub-Category(s) | Maintenance, Paving/Reconstruction, Site Development, Water Lines |
Contracting Method | Competitive Bids |
Project Status | Contract Award, Construction start expected October 2023 |
Bids Due | View project details and contacts |
Estimated Value | $195,319 [brand] Estimate |
Plans Available from | Civil Engineer |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Construct the SE Archer Avenue Extension including all materials, labor and equipment necessary for installation of approximately: 5,300 CY of Grading, 1,000 SY of Subgrade Preparation, 160 CY of 6" Modified Subbase, 830 SY of 9" PCC Pavement, 230 LF of subdrain, signing, erosion control, surface restoration, and miscellaneous related work and appurtenances. Each bidder shall accompany its bids with bid security as defined in Iowa Code Section 26.8, as security that the successful bidder will enter into a contract for the work bid upon and will furnish after the award of contract a corporate surety bond, in a form acceptable to the City for the faithful performance of the contract and guaranteeing payment to all persons supplying labor and/or materials in the execution of the work provided for in the contract, in an amount equal to 100% of the amount of the contract. Additionally the bidder must provide the City with a guarantee of maintenance of said improvement for a period of four (4) years from the time of acceptance by the City. The bidder's security shall be in an amount equal to ten percent (10%) of the total amount of the bid and shall be in the form of a cashier's check or a certified check drawn on an FDIC insured bank in Iowa or on an FDIC insured bank chartered under the laws of the United States; or a certified share draft drawn on a credit union in Iowa or chartered under the laws of the United States; or a bid bond on the form provided in the contract documents with corporate surety satisfactory to the City. The bid shall contain no condition except as provided in the specifications. If the bidder fails to execute the contract and to furnish an acceptable performance, payment, and maintenance bond or provide a Certificate of Insurance within ten (10) days after acceptance of the bid by the City, the bid security may be forfeited or cashed by the City as liquidated damages Final Project Completion shall occur on or before May 30, 2024. The duration of the work is critical to the project so as to minimize damage to other streets and public infrastructure and the disruption associated with the project to the public. Damages in the amount of Seven Hundred Fifty Dollars ($750.00) per calendar day will be assessed for each day the work shall remain uncompleted after the end of the contract period at the sole discretion of the City which at the option of the City may be deducted from any retainage prior to release, the final payment to contractor, or through the commencement of a cause of action by the City, in the City's sole discretion. The selection by the City of any particular course of action hereunder is not exclusive and shall not preclude the pursuit of additional remedies by the City. In the event the City institutes legal proceedings, the Contractor shall be responsible for any and all attorney's fees and expenses. Liquidated damages will be imposed for both Intermediate and Final Project Completion Dates. |
||||||
Details |
|
||||||
Bidder's List | View project details and contacts | ||||||