Similar Projects
Last Updated | 08/30/2022 01:01 PM |
Project Title | Lexington Veterans Pavilion at Kirkpatrick Memorial Park |
Physical Address | View project details and contacts |
City, State (County) | Lexington, NE 68850 (Dawson County) |
Category(s) | Entertainment/Recreation, Heavy and Highway |
Sub-Category(s) | Misc. Recreational, Site Development |
Contracting Method | Competitive Bids |
Project Status | Construction start expected August 2022 |
Bids Due | View project details and contacts |
Estimated Value | $1,160,000 [brand] Estimate |
Plans Available from | Copy Center |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | The Owner will consider the bids received for the furnishing of said labor, materials and equipment necessary for the proper construction of the aforesaid project. The General, Mechanical and Electrical, will be under one Bid. All subcontractor quotations shall be sent to the General Contractor. Bid Security is required to be submitted with bid proposal form. Make payable to City of Lexington in the amount of 5% of the Lump Sum Bid Amount. Bid Security shall be of cashiers check, certified check, or Bid Bond issued by a Surety licensed to conduct business in the State of Nebraska. Form of Bid Bond is AIA Document A310. Any agent signing a bid bond on behalf of the Surety must attach a Power of Attorney effectively evidencing the agent's authority to bind the Surety to the performance of the Bid Bond. Performance Bond: The Contractor shall be required to furnish acceptable bonds to complete the work and pay for all labor and materials used, said bonds to be in the amount of 100% of total amount of the Contract. See Document A701, Instructions to Bidders. Taxes: The Contractor by virtue of his contract with City of Lexington, becomes a purchasing agent for the Owner on their behalf and under Statute 77-2702 does not pay sales tax. Davis-Bacon Act: This project is subject to the provisions and mandates of the Davis-Bacon Act as administered by the United States Department of Labor, Wage and Hour Division. 1. Contractor(s) must provide a breakout between all Materials and Labor and separate Applications for Payment must be submitted for the Davis-Bacon Act applicable work and the NON-Davis-Bacon Act applicable work. Insurance: Prior to the start of the work, completed copies of the Certificate of Insurance, AIA Document G705 shall be submitted to the Owner and Architect. There is NO Pre-Bid Conference scheduled. 1. Time: 2:00 p.m.. 2. Place: City of Lexington. 3. Location: 1002 N. Monroe, Lexington, NE 68850. Addenda may be issued during the bidding period. All Addenda become part of Contract Documents. Include resultant costs in the Bid Amount. Verbal answers are not binding on any party. Clarifications requested by bidders must be in writing not less than four (4) days before date set for receipt of bids. The reply will be in the form of an Addendum, a copy of which will be forwarded to known recipients. No technical questions will be answered by the Architect's /Engineer's office(s) during the twenty-four (24) hours immediately preceding the bid opening time and date. Owner reserves the right to accept or reject any or all offers and to pass upon the regularity or waive any irregularities of any bid. The Owner intends, but shall not be required, to interview the two (2) lowest responsible bidders to determine the lowest responsible bidder. Any award of contract shall be made to the lowest responsible bidder, taking into consideration the best interests of the Owner, the quality performance of the Contractor, and his ability to perform the work. The decision to award the contract shall be in the sole discretion of the Owner. After acceptance by Owner, Architect on behalf of Owner, will issue to the successful bidder, a written Notice To Proceed. |
||||||||||||||||||||||||||||||
Details |
|
||||||||||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |