Last Updated | 07/18/2023 09:40 AM |
Project Title | Unit 8 Superheat Replacement - City of Ames |
Physical Address | View project details and contacts |
City, State (County) | Ames, IA 50010 (Story County) |
Category(s) | Heavy and Highway, Industrial/Manufacturing |
Sub-Category(s) | Power Plant, Site Development |
Contracting Method | Competitive Bids |
Project Status | Design Development, Construction start expected September 2023 |
Bids Due | View project details and contacts |
Estimated Value | $6,550,000 [brand] Estimate |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | This project is to replace the tubing in the superheats section of the unit 8 boiler. After switching from coal to natural gas, the tubes were found to be degrading much faster than anticipated. The high moisture created during the combustion of natural gas combined with chlorides and acidic gases from RDF combustion cause the metal tube surface to corrode very quickly. The current superheat tube thicknesses have been dramatically reduced and need to be replaced. An Inconel coating will be added to the new tubes to help them stand-up-to the harsh environment. Project is included City of Ames FY 2019-2024 CIP Page 69 _______________________________________________________________________________________________________________________ This project is to replace the tubing in the superheats section of the unit 8 boiler. After switching from coal to natural gas, the tubes were found to be degrading much faster than anticipated. The high moisture created during the combustion of natural gas combined with chlorides and acidic gases from RDF combustion cause the metal tube surface to corrode very quickly. The current superheat tube thicknesses have been dramatically reduced and need to be replaced. An Inconel coating will be added to the new tubes to help them stand-up-to the harsh environment. The project is included in the city's 2019-2024 Capital Improvement Program (CIP). As of February 12, 2020, further details regarding design and construction have not been identified.* *Project information has been obtained through a public capital improvement plan (CIP). A CIP is a financial schedule for short- and long-range projects which is updated regularly. Information listed in the CIP often evolves based on funding availability and the project details, including timeline and value, are subject to change. The content management team will continue to pursue additional details as they become available. As of July 18, 2023, no rebid information available |
||||||||||||||||||||||||||||||||||||||||||||||
Details |
|
||||||||||||||||||||||||||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||||||
Project Documents |
![]() Engineered Spec Sheet ![]() Architectural Plans ![]() Other Documents |