Similar Projects
Last Updated | 02/27/2023 04:05 PM |
Project Title | Cure-In-Place Pipe (CIPP) 2020 |
Physical Address | View project details and contacts |
City, State (County) | Spokane, WA 99201 (Spokane County) |
Category(s) | Heavy and Highway, Sewer and Water |
Sub-Category(s) | Site Development, Water Lines |
Contracting Method | Competitive Bids |
Project Status | Contract Award, Construction start expected May 2022 |
Bids Due | View project details and contacts |
Estimated Value | $1,354,009 [brand] Estimate |
Plans Available from | Civil Engineer |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | This project consists of the installation of the following quantities of cure-in-place pipe (CIPP): 8" - approx. 4,300 LF, 10" - approx. 2,000 LF, 12" - approx. 3,500 LF, 14" - approx. 500 LF, 20" - approx. 1,200 LF, 24" - approx. 2,300 LF for an approximate total of 13,800 LF. Also included are side sewer reconnections and approximately 20 service connection repairs. The City of Spokane, in accordance with the provisions of Title VI of the Civil Rights Act of 1964 (78 Stat. 252,42 U.S.C. 2000d to 2000d-4) and the Regulations, hereby notifies all bidders that will affirmatively ensure that any contract entered into pursuant to this advertisement, disadvantaged business enterprises will be afforded full and fair opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of race, color, or national origin in consideration for an award. Bids shall be submitted on the forms provided in accordance with the provisions of the Specifications. Irregular bid proposals will be rejected in accordance with the specifications. Cashier's check, a certified check or surety bond in the sum of five percent (5%) of the Total Project Bid must accompany the copy of the bid filed with the City Clerk. Successful bidder shall execute the Contract within FIVE (5) calendar days after receiving the Contract. Should the successful bidder fail to enter into such contract and furnish satisfactory performance bond within the time stated herein, the bid proposal deposit shall be forfeited to the City of Spokane. The City of Spokane will normally award this Contract or reject bids within FORTYFIVE (45) calendar days after the time set for the bid opening. If the lowest responsible Bidder and the City of Spokane agree, this deadline may be extended. If they cannot agree on an extension by the 45-calendar day deadline, the City of Spokane reserves the right to Award the Contract to the next lowest responsible Bidder or reject all Bids. Range: $1,500,000.00 to $1,750,000.00 *The value for this project is based on a financial range. The value is listed as the highest possible cost from the range provided by a stakeholder or official project document. |
||||
Details |
|
||||
Bidder's List | View project details and contacts | ||||
Prospective Bidders | View project details and contacts | ||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |