Last Updated | 02/11/2021 11:47 AM |
Project Title | Wastewater Treatment Plant Switch Gear and Transformer Upgrade Project |
Physical Address | View project details and contacts |
City, State (County) | Lancaster, PA 17603 (Lancaster County) |
Category(s) | Single Trades |
Sub-Category(s) | Electric |
Contracting Method | Competitive Bids. |
Project Status | Results |
Bids Due | View project details and contacts |
Estimated Value | $3,000,000 |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | The work is generally described as the installation, repair and replacement of switch gear and transformers so as to upgrade the same at the Lancaster Advanced Wastewater Treatment Plant located at 1220 New Danville Pike, Lancaster, Pennsylvania. 1. Demolition of two 15kV switch gear line ups, four mediam voltage, pad-mounted transformers and medium voltage cables; 2. Installation of one 1200 A 15kV outdoor rated, walk-in switch gear line up and associated foundation; 3. Relocation of PPL service entrance and associated duct banks; 4. Installation of two electrical manholes and associated duct banks; 5. Installation of four medium voltage, pad-mounted transformers, installation of one new foundation and repair of existing foundations; 6. Installation of four medium voltage, pad-mounted automatic transformer switches and associated foundations; 7. Installation of medium voltage cabling to all new and existing medium voltage equipment with deadbrake junction bars in manholes; 8. Associated E and S work to facilitate new foundation in duct banks; 9. Testing and commissioning; and 10. Other related matters. |
||
Details |
|
||
Bidder's List | View project details and contacts | ||
Prospective Bidders | View project details and contacts | ||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |