Last Updated | 07/22/2022 09:12 AM |
Project Title | Duke Energy Substation Access Road Project |
Physical Address | View project details and contacts |
City, State (County) | Jeffersonville, IN 47130 (Clark County) |
Category(s) | Heavy and Highway, Sewer and Water |
Sub-Category(s) | Maintenance, Paving/Reconstruction, Site Development, Water Lines |
Contracting Method | Competitive Bids |
Project Status | Construction start expected August 2022 |
Bids Due | View project details and contacts |
Estimated Value | $1,009,143 [brand] Estimate |
Plans Available from | Civil Engineer |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | No late Bids will be accepted. The Work includes the construction of approximately 1,200 linear feet of a three-lane urban roadway along with approximately 750 linear feet of storm sewer installation. SUBSTANTIAL COMPLETION - November 4, 2022 Bids from Bidders who are not on the Plan Holders List may be returned as not being responsive. Plan Holders are requested to provide an e-mail address if they wish to receive addenda and other information electronically. Plan Holders are requested to designate whether they are a prime Contractor, Subcontractor, or Supplier if they want this information posted on the project Plan Holders List. Bid Proposals shall be properly and completely executed on forms incorporated in the Contract Documents, including State Form 52414 (Form 96), revised 2013 or later. Questions should be directed in writing to Seth W. Winslow, P.E. at Strand Associates, Inc., 325 West Main Street, Suite 710, Louisville, KY 40202 or seth.winslow@strand.com. In accordance with IC 22-5-1.7-3, Contractors and Sub-Contractors are required to enroll in and verify the work eligibility status of all its newly hired employees through the E-Verify program. In accordance with IC 5-22-16.5, Contractors entering into a contract with the OWNER will be required to provide an Indiana Iran Investment Certification. In accordance with IC 4-13-18, Contractor shall submit an Employee Drug Testing Plan with their Bid and Contractors of any tier as defined in IC 5- 16-13-4 must comply with the drug testing requirements. No Bidder may withdraw his proposal within a period of 60 days following the date set for opening Bids. The OWNER reserves the right to retain any and all Bids for a period of not more than 60 days, and said Bids shall remain in full force and effect during said time. The OWNER further reserves the right to waive informalities, and to award the contract to any Bidder to the advantage of the OWNER, or to reject all Bids. |
||||||||||
Details |
|
||||||||||
Bidder's List | View project details and contacts | ||||||||||
Prospective Bidders | View project details and contacts | ||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |