Similar Projects
Last Updated | 06/01/2020 04:24 AM |
Project Title | Constructing the Resurfacing and Traffic Stripe on South Park Avenue from the Intersection of Taylor Road to Ross Clark Circle in Dothan |
Physical Address | View project details and contacts |
City, State (County) | AL (Houston County) |
Category(s) | Heavy and Highway |
Sub-Category(s) | Paving/Reconstruction |
Contracting Method | Competitive Bids. |
Project Status | Results |
Bids Due | View project details and contacts |
Estimated Value | $256,006 to $312,896 |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | 401A004 Bituminous Treatment E 15,088 SQYD 405A000 Tack Coat 1,509 Gal 407B000 Joint Sealant For Hot Mix Asphalt Pavement 2 Mile 424A360 Superpave Bituminous Concrete Wearing Surface Layer, 1/2" Maximum Aggregate Size Mix, ESAL Range C/D 1,313 Ton 424B657 Superpave Bituminous Concrete Upper Binder Layer, Leveling, 1/2" Maximum Aggregate Size Mix, ESAL Range C/D 790 Ton 600A000 Mobilization (1.000) LS 698A000 Construction Fuel (Maximum Bid Limited to $ 14,000.00) (1.000) LS 701C000 Broken Temporary Traffic Stripe 1 Mile 701C001 Solid Temporary Traffic Stripe 4 Mile 703D001 Temporary Traffic Control Markings 144 SQFT 703E001 Temporary Traffic Control Legends 148 SQFT 740B000 Construction Signs 325 SQFT 740E000 Cones (36 Inches High) 30 Each 740M001 Ballast For Cone 30 Each 740O000 Pilot Car 1 Each |
||||||
Details |
|
||||||
Bidder's List | View project details and contacts | ||||||
Prospective Bidders | View project details and contacts | ||||||
Project Documents |