Similar Projects
Last Updated | 06/23/2023 06:04 PM |
Project Title | USS Equipment Replacement - Phase 1 |
Physical Address | View project details and contacts |
City, State (County) | Miami, FL 33132 (Miami-Dade County) |
Category(s) | Single Trades |
Sub-Category(s) | Service/Term Contracts |
Contracting Method | Competitive Bids |
Project Status | Sub-Bidding, Construction start expected August 2023 |
Bids Due | View project details and contacts |
Estimated Value | $3,104,504 [brand] Estimate |
Plans Available from | Agency's Affiliate |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Liquidated Damages: YES $$ Per Day: $2,045.84 Contract No: MCC 7040 Plan - CICC 7040-0/07 Scope of Work: (Contractor must obtain and submit all permits prior to performing any work). Work under this Contract includes furnishing of all supervision, labor, materials, tools, equipment and performing all operations required to construct the Work in accordance with the Contract Documents. Replace Unit Substation equipment located at four (4) Metro Rail stations, and Unit Substations (2) equipment located at William Lehman Center. Calendar Days for Project Completion: 1825 |
||||||
Details |
|
||||||
Bidder's List | View project details and contacts | ||||||
Prospective Bidders | View project details and contacts | ||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |