Similar Projects
Last Updated | 01/24/2023 11:34 PM |
Project Title | Breezemont Tributary - City of Maryland Heights |
Physical Address | View project details and contacts |
City, State (County) | Maryland Heights, MO 63043 (Saint Louis County) |
Category(s) | Heavy and Highway, Sewer and Water |
Sub-Category(s) | Shoreline/Erosion/Drainage, Site Development, Water Lines |
Contracting Method | Competitive Bids |
Project Status | Conceptual Design, Construction start expected September 2024 |
Bids Due | View project details and contacts |
Estimated Value | $400,000 [brand] Estimate |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | https://files4.1.revize.com/marylandheightsmo/Admin%20and%20Finance/Budget%20Sections/2023/2023%20CIP%20Final.pdf This project stabilizes the channel and banks along the reach of Breezemont located in Brookside Subdivision common ground between Brookmont Drive on and Breezemont Drive/Foxwood Drive on the south, using grade control and bio-stabilization techniques. Existing storm sewer infrastructure located within tributary reach that is failed or in need of attention will be repaired or replaced. forestry practices may be used to restore and enhance the riparian Corridor. As of January 25, 2023, this project is currently in the FY 2023-2027 CIP . Funding for this project is allotted in the city's capital improvement plan for construction Fy 2024. A firm timeline has not been established; however, construction is scheduled for Fiscal Year 2024. _________________ This project stabilizes the channel and banks along the reach of Breezemont located in Brookside Subdivision common ground between Brookmont Drive on and Breezemont Drive/Foxwood Drive on the south, using grade control and bio-stabilization techniques. Existing storm sewer infrastructure located within tributary reach that is failed or in need of attention will be repaired or replaced. forestry practices may be used to restore and enhance the riparian Corridor. This project is included City of Maryland Heights FY 2022 - 2026 Capital Improvement plan . As of March 05,2022, further details regarding design and construction have not been identified. *Project information has been obtained through a public capital improvement plan (CIP). A CIP is a financial schedule for short- and long-range projects which is updated regularly. Information listed in the CIP often evolves based on funding availability and the project details, including timeline and value, are subject to change. The content management team will continue to pursue additional details as they become available. |
||||||
Details |
|
||||||
Bidder's List | View project details and contacts | ||||||
Prospective Bidders | View project details and contacts | ||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |