Reported | 06/24/2022 12:00 AM |
Project Title | Repair Ammunition Wharf W2 |
Physical Address | View project details and contacts |
City, State (County) | HI (Honolulu County) |
Category(s) | Heavy and Highway |
Sub-Category(s) | Dock/Pier/Marine |
Contracting Method | Competitive Bids. |
Project Status | Bidding, Construction Start Expected August 2022 |
Bids Due | View project details and contacts |
Estimated Value | $25,000,000 to $100,000,000 |
Plans Available from | Civil Engineer |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Project proposes to repair Ammunition Wharf W2 by replacing it with a reinforced concrete wharf on concrete piles built to current standards. The project will be divided into two phases, fiscal year FY22 and FY23. Phase 1 will consist of the portion of W2 closest to W1 and Phase 2 will consist of the portion of W2 closest to W3. Scope of the work for each phase is identical and will include demolition of the existing timber pile fender system and wharf deck. Sheet piling will be installed inboard of the wharf structure. A fender system will consist of pre-cast concrete piles and plastic wales and chocks. Pile clusters will be provided to accommodate foam filled floating fenders. The project will also include the reconstruction of wastewater and portable water utility systems, phone lines and grounding system for lighting protection. Utilities will be placed into a utility trench built into the wharf deck. Permanent oil spill containment boom, safety ladders, life ring cabinets, fire alarm system and mooring hardware will be installed. |
||
Details |
|
||
Bidder's List | View project details and contacts | ||
Prospective Bidders | View project details and contacts | ||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |