Similar Projects
Last Updated | 08/08/2022 12:33 PM |
Project Title | Designed Overlay, ADA Improvements and Rumble Strip |
Physical Address | View project details and contacts |
City, State (County) | La Grange, IL 60525 (Cook County) |
Category(s) | Heavy and Highway |
Sub-Category(s) | Maintenance, Paving/Reconstruction, Sidewalks/Parking Lot, Site Development |
Contracting Method | Bids by Invitation, Competitive Bids |
Project Status | Construction start expected September 2022 |
Bids Due | View project details and contacts |
Estimated Value | $3,271,012 [brand] Estimate |
Plans Available from | Civil Engineer |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | (22,113-Ft) Designed Overlay, ADA Improvements and Rumble Strip located on Willow Springs Road from IL. 171 (Archer Ave) to North of 55th St. in Cook County. DESCRIPTION OF PROJECT The scope of this project is pavement resurfacing (Designed Overlay) and ADA sidewalk ramp Improvement, new shoulders, and milled rumble strip. The work to be performed under this contract shall consist of pavement patching, milling of existing HMA surface, placing HMA surface course and HMA binder course, drainage structures adjustment and cleaning, placement of pavement markings, installation of sidewalk ramp improvements, and all incidental and collateral work necessary to complete the project as shown on the plans and as described herein. Region 1 District 1 Federal Project # N/A County(s) Cook Key Route(s) FAU 2697 Marked Route(s) Willow Springs Road Section(s) 2021-019-RS-SR&SW State Job #(s) C-91-154-21 PPS #(s) 1-79106-0000 Completion Date : 65 Working Days Questions not accepted as of July 26, 2022 04:30 PM. Questions directed to: IDOT Contracts Office Harry R. Hanley Building Room 326 2300 South Dirksen Parkway Springfield, IL 62764 (217) 782-7806 Fax: (217) 785-1141 TDD: (217) 524-4875 DOT.DE-Contracts@illinois.gov Unless otherwise indicated, a proposal guaranty is required by bid bonds, cashiers check or properly certified check for not less than 5 (five) percent of the bid amount. If the proposal is accepted and the bidder is declared not responsive, it is hereby agreed that the amount of the proposal guaranty will become the property of the State of Illinois and shall be considered as payment of damages due to the delay and other causes suffered by the State because of the failure to adhere to the procedures required. Otherwise, the bid bond will become void or the proposal guaranty check will be returned to the bidder. Contractors who desire to become prequalified or to renew their prequalification for this letting must file with the Department of Transportation, Bureau of Construction, Room 322, 2300 South Dirksen Parkway, Springfield, Illinois 62764, a Contractor's Statement of Experience and Financial Condition no later than 4:30 PM prevailing local time, July 15, 2022. A contractor will not be prequalified for this letting unless the statement is received before the time and day established. The Department reserves the right to reject any and all bids, to waive minor or immaterial irregularities, informalities or technicalities, to advertise for new bids, or to request confirmation or clarification from any bidder regarding a bid. ILDOT - 013 - Designed Overlay, ADA Improvements and Rumble Strip |
||||||||||
Details |
|
||||||||||
Bidder's List | View project details and contacts | ||||||||||
Prospective Bidders | View project details and contacts | ||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |