Similar Projects
Last Updated | 04/26/2022 12:13 AM |
Project Title | 2022 System Wide Distribution Improvements |
Physical Address | View project details and contacts |
City, State (County) | Kindred, ND (Cass County) |
Category(s) | Sewer and Water |
Sub-Category(s) | Water Lines |
Contracting Method | Competitive Bids. |
Project Status | Results |
Bids Due | View project details and contacts |
Estimated Value | $200,000 [brand] Estimate |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | The Work is comprised of one (1) Contract with one (1) Base Bid and eight (8) Bid Alternates: Contract No. 1 – Pipeline Construction. The Base Bid and Alternates have an ‘A’ Option - PVC Pipeline Construction and a ‘B’ Option - Poly Pipeline Construction. Contract No. 1 will award the Base Bid ‘A’ Option or Base Bid ‘B’ Option with or without any combination of the alternates; Alternates with an ‘A’ Option or a ‘B’ Option will only award the ‘A’ Option or the ‘B’ Option if the corresponding alternate is accepted for award. Contractor must bid the Base Bid and all alternates. The Contractor is allowed to bid either the ‘A’ Option or the ‘B’ Option, both the ‘A’ Option and the ‘B’ Option, or any combination of the ‘A’ Option and ‘B’ Option for the Base Bid and all alternates. The Work is generally described as follows: Contract No. 1: Pipeline Construction: 1. Base Bid – Option A or Option B: Construction of rural water pipelines consisting of furnishing and installing the following approximate quantities: 4,700 feet of 3-inch pipeline, 300 feet of 3-inch DR 11 IPS Poly directional bores, one (1) steel railroad cased bores with POLY carrier pipe; two (2) tie-ins to existing system, two (2) 3-inch gate valves and all associated fittings and appurtenances, restoration, flushing and testing, signage, seeding, and gravel. 2. Alternates No. 1 – No. 8 to Contract No. 1 – Option A or Option B: Construction of rural water pipelines consisting of furnishing and installing the following approximate quantities: 750 feet of 2-inch IPS pipeline, 14,650 feet of 3-inch IPS pipeline, 126,500 feet of 4-inch IPS pipeline, 150 feet of 2-inch DR 11 IPS Poly directional bores, 1,750 feet of 3-inch DR 11 IPS Poly directional bores, 7,450 feet of 4-inch DR 11 IPS Poly directional bores, two (2) steel railroad cased bores with Poly carrier pipe, twenty (20) tie-ins to existing system, thirty-seven (37) gate valves ranging in size from 1.5-inch to 6-inch, nine (9) 1-inch flush/air blow off valve, and all associated fittings and appurtenances, restoration, flushing and testing, signage, seeding, and gravel. Note Alternate No. 6 Option B upsizes the pipeline sizes from Option A 3-inch PVC to 4-inch Poly and Alternate No. 7 Option B upsizes the pipeline sizes from Option A 4-inch PVC to 6-inch Poly. The work for Contract No. 1 must be completed no later than the following: 1. Base Bid a. Substantial Completion – October 15, 2022 b. Final Completion – November 1, 2022 2. Alternates No. 1 through No. 8 to Contract No. 1 a. Substantial Completion – July 1, 2023 b. Final Completion – July 15, 2023 |
||
Details |
|
||
Bidder's List | View project details and contacts | ||
Prospective Bidders | View project details and contacts | ||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |