Project Title | Pier E Sewer Lift Stations 110 and 112 Modifications |
Physical Address | View project details and contacts |
City, State (County) | Long Beach, CA 90802 (Los Angeles County) |
Category(s) | Heavy and Highway, Sewer and Water |
Sub-Category(s) | Lift and Pump Stations, Site Development |
Contracting Method | Competitive Bids |
Project Status | Results, Construction start expected July 2023 |
Bids Due | View project details and contacts |
Estimated Value | $2,734,660 [brand] Estimate |
Plans Available from | Civil Engineer |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | **As of July 13,2023 , this project has not yet been awarded. The project is expected to be awarded on July 24,2023.** All questions, including requests for interpretation or correction, or comments regarding the Contract Documents, must be submitted no later than May 9, 2023, at 5 p.m. Questions received after the pre-Bid question deadline will not be accepted. Scope of Services Summary Description of the Work. The Work required by this Contract includes, but is not limited to, the following: retrofitting construction of two existing sewer lift stations including modifying well floor slab; installing submersible pumps, valve vaults, and associate piping; providing electrical modifications and PLC instrumentations for SCADA connection; constructing manhole; and implementing temporary sewer bypass measures for the retrofitting construction. See Section 01 11 00, Summary of Work in the Technical Specifications. All questions, including requests for interpretation or correction, or comments regarding the Contract Documents, must be submitted no later than May 9, 2023, at 5 p.m. Questions received after the pre-Bid question deadline will not be accepted. The Estimated Bid Value has been changed to $2,292,000. The combined SBE/VSBE participation goal for this Project is thirty percent (30%) of total bid value. The combined SBE/VSBE participation goal shall include a minimum five percent (5%) of total bid value as VSBE. Contract Time and Liquidated Damages. The Contractor shall achieve Substantial Completion of Work within 570 calendar days and Affidavit of Final Completion of the Project within 660 calendar day |
||||||||||||||||||||||||||||||||||||||||||||||
Details |
|
||||||||||||||||||||||||||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |