Project Title | Roadway Reconstruction and Related Work on a Section of Route 143 (Old North and Williamsburg Roads) (Phase 1) |
Physical Address | View project details and contacts |
City, State (County) | Cummington, Worthington, MA 01026 (Hampshire County) |
Category(s) | Heavy and Highway |
Sub-Category(s) | Paving/Reconstruction |
Contracting Method | Competitive Bids. |
Project Status | Results |
Bids Due | View project details and contacts |
Estimated Value | $7,458,678 |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | "1.000","Ls","Schedule Of Operations - Fixed Price $57000","100." "1.000","a","Clearing And Grubbing","101." "0.100","a","Selective Clearing And Thinning","102." "115.000","Ea","Tree Protection-Armoring & Pruning","102.511" "370.000","Ft","Tree And Plant Protection Fence","102.521" "10.000","Hr","Arborist","102.55" "15.000","Ea","Tree Removed - Diameter Under 24 Inches","103." "16.000","Ea","Tree Removed - Diameter 24 Inches And Over","104." "6.000","Ea","Stump Removed","105." "7000.000","Cy","Unclassified Excavation","120.1" "10.000","Cy","Muck Excavation","123." "900.000","Cy","Class a Trench Excavation","141." "50.000","Cy","Test Pit For Exploration","141.1" "260.000","Cy","Class b Trench Excavation","142." "150.000","Cy","Class b Rock Excavation","144." "24.000","Ea","Drainage Structure Removed","146." "310.000","Cy","Special Borrow","150.1" "1700.000","Cy","Gravel Borrow","151." "90.000","Cy","Gravel Borrow For Bridge Foundation","151.1" "1200.000","Cy","Gravel Borrow For Backfilling Structures And Pipes","151.2" "120.000","Cy","Gravel Borrow For Slope Treatment","151.3" "10.000","Cy","Controlled Density Fill - Non-Excavatable","153.1" "270.000","Ton","Crushed Stone","156." "6000.000","Sy","Fine Grading And Compacting - Subgrade Area","170." "1.000","Ls","Environmental Health And Safety Program","180.01" "16.000","Hr","Personal Protection Level c Upgrade","180.02" "16.000","Hr","Licensed Site Professional Services","180.03" "25.000","Ton","Disposal Of Unregulated Soil","181.11" "10.000","Ton","Disposal Of Regulated Soil - In-State Facility","181.12" "10.000","Ton","Disposal Of Regulated Soil - Out-Of-State Facility","181.13" "5.000","Ton","Disposal Of Hazardous Waste","181.14" "1.000","Ls","Inspection And Testing For Asbestos","182.1" "100.000","Ft","Removal Of Asbestos","182.2" "25.000","Ton","Disposal Of Treated Wood Products","184.1" "21.000","Ea","Catch Basin","201." "1.000","Ea","Manhole","202." "1.000","Ea","Manhole (9 To 14 Foot Depth)","202.2" "16.000","Ea","Drop Inlet, Type Af","206.1" "4.000","Ea","Drop Inlet Rebuilt","209.5" "2.000","Ea","Drop Inlet - Precast Concrete Throat","209.51" "94.000","Ea","Drainage Structure Adjusted","220." "65.000","Ft","Drainage Structure Rebuilt","220.2" "1.000","Ea","Drainage Structure Change In Type","220.3" "60.000","Ea","Drainage Structure Remodeled","220.5" "9.000","Ea","Frame And Cover","221." "24.000","Ea","Frame And Grate - Massdot Cascade Type","222.1" "30.000","Ea","Frame And Grate - Massdot Drop Inlet","222.2" "5.000","Ea","Frame And Grate (Or Cover) Removed And Stacked","223.1" "5.000","Ea","Frame And Grate (Or Cover) Removed And Discarded","223.2" "14.000","Ea","12 Inch Hood","224.12" "40.000","Cy","Removal Of Drainage Structure Sediment","227.3" "5900.000","Ft","Removal Of Drainage Pipe Sediment","227.31" "1300.000","Ft","12 Inch Drainage Pipe - Option","234.12" "50.000","Ft","15 Inch Drainage Pipe - Option","234.15" "100.000","Ft","18 Inch Drainage Pipe - Option","234.18" "90.000","Ft","24 Inch Drainage Pipe - Option","234.24" "30.000","Ea","12 Inch Drainage Pipe Flared End - Option","235.12" "1.000","Ea","18 Inch Drainage Pipe Flared End - Option","235.18" "3.000","Ea","24 Inch Drainage Pipe Flared End - Option","235.24" "200.000","Ft","12 Inch Ductile Iron Pipe","238.12" "1.000","Ea","15 Inch Reinforced Concrete Pipe Flared End","242.15" "100.000","Sy","Stone For Pipe Ends","258." "810.000","Ft","12 Inch And Under Pipe Removed And Relaid","270.12" "90.000","Ft","18 Inch Pipe Removed And Relaid","270.18" "20.000","Sy","Hot Mix Asphalt Waterway","280." "110.000","Ft","4 Inch Ductile Iron Water Pipe (Rubber Gasket)","302.04" "130.000","Ft","6 Inch Ductile Iron Water Pipe (Rubber Gasket)","302.06" "650.000","Ft","8 Inch Ductile Iron Water Pipe (Rubber Gasket)","302.08" "600.000","Lb","Ductile Iron Fittings For Water Pipe","309." "100.000","Ft","1 Inch Copper Tubing Type k","347.1" "1.000","Ea","4 Inch Gate And Gate Box","350.04" "2.000","Ea","6 Inch Gate And Gate Box","350.06" "4.000","Ea","8 Inch Gate And Gate Box","350.08" "1.000","Ea","6 Inch Gate Box","357.06" "1.000","Ea","8 Inch Gate Box","357.08" "1.000","Ea","12 Inch Gate Box","357.12" "22.000","Ea","Gate Box Adjusted","358." "10.000","Ea","1 Inch Corporation Cock","363.1" "1.000","Ea","Hydrant - Removed And Reset","376.2" "19.000","Ea","Service Box","381." "19.000","Ea","Service Box Removed And Reset","381.1" "75.000","Ea","Service Box Adjusted","381.3" "570.000","Cy","Dense Graded Crushed Stone For Sub-Base","402." "22000.000","Ft","Pavement Milling Mulch For Shoulders","402.13" "850.000","Ton","Crushed Stone For Blending","403.1" "68100.000","Sy","Full Depth Reclamation With Emulsified Asphalt Stabilization","403.2" "68100.000","Gal","Emulsified Asphalt For Stabilization","403.21" "1200.000","Sy","Pavement Micromilling","415." "10.000","Sy","High Early Strength Cement Concrete Base Course","431." "220.000","Mgl","Water For Roadway Dust Control","443." "6200.000","Ton","Superpave Surface Course – 9.5 Polymer (Ssc – 9.5 - p)","450.221" "7200.000","Ton","Superpave Intermediate Course - 12.5 (Sic -12.5)","450.31" "13400.000","Ton","Superpave Intermediate Course - 19.0 (Sic - 19.0)","450.32" "100.000","Ton","Hma For Patching","451." "7400.000","Gal","Asphalt Emulsion For Tack Coat","452." "24400.000","Ft","Hma Joint Sealant","453." "140.000","Ton","Hot Mix Asphalt For Miscellaneous Work","472." "1000.000","Ft","Sawcutting Asphalt Pavement For Box Widening","482.5" "490.000","Ft","Granite Curb Type Va4 - Straight","504." "1100.000","Ft","Granite Curb Type Va4 - Curved","504.1" "500.000","Ft","t-100 Traversable Granite Curb","507.1" "30.000","Ft","Granite Transition Curb For Wheelchair Ramps - Straight","509." "3.000","Ea","Granite Curb Inlet - Straight","514." "2.000","Ea","Granite Curb Inlet - Curved","515." "1100.000","Ft","Curb Removed And Reset","580." "1700.000","Ft","Curb Removed And Stacked","590." "340.000","Ft","Curb Removed And Discarded","594." "5700.000","Ft","Guardrail, Tl-3 (Single Faced)","620.13" "12.000","Ea","Trailing Anchorage","627.1" "2.000","Ea","Guardrail Tangent End Treatment, Tl-3","627.83" "23.000","Ea","Guardrail Flared End Treatment, Tl-3","627.93" "1.000","Ea","Transition To Nchrp 350 Guardrail","628.21" "4.000","Ea","Transition To Bridge Rail","628.24" "5000.000","Ft","Highway Guard Removed And Discarded","630.2" "5.000","Cy","Stone Masonry Wall Removed And Rebuilt In Cement Mortar","690." "1660.000","Ft","Balance Stone Wall Removed And Rebuilt","691." "100.000","Ea","Silt Sack","697.1" "400.000","Sy","Geotextile Fabric For Separation","698.3" "10.000","Sy","Cement Concrete Sidewalk","701." "270.000","Sy","Stamped Cement Concrete Island","701.3" "600.000","Ton","Hot Mix Asphalt Driveway","703." "3.000","Sy","Flagstone Walk Removed And Reset","705.1" "2.000","Ea","Bound - Plain Granite","710.4" "2.000","Ea","Bound Removed And Reset","711." "20.000","Ea","Rural Mail Box Removed And Reset","715." "19.000","Mo","Engineers Field Office And Equipment (Type a)","740." "1.000","Ls","Mobilization","748." "6000.000","Cy","Loam Borrow","751." "1.000","Ls","Wetland Mitigation Areas","755.35" "40.000","Hr","Wetland Specialist","755.75" "1.000","Ls","Wetland Monitoring Report","755.76" "1.000","Ls","Npdes Stormwater Pollution Prevention Plan","756." "37800.000","Sy","Seeding-Low Upland Mix","765.411" "8900.000","Ft","Sediment Control Barrier","767.121" "5.000","Ton","Straw Mulch","767.3" "6600.000","Ft","Pavement Milling Mulch Under Guard Rail","769." "620.000","Ft","2 Inch Electrical Conduit Type Nm - Plastic (Ul)","804.2" "1240.000","Ft","4 Inch Electrical Conduit Type Nm - Plastic -(Ul)","804.4" "2480.000","Ft","6 Inch Electrical Conduit Type Nm - Plastic -(Ul)","804.6" "620.000","Ft","Conduit Encased In Concrete - Sd 4.041","810." "1.000","Ea","Telephone Manhole - 3x3x3 Foot","811.111" "1.000","Ea","Electric Manhole - 5x10x7 Foot","811.131" "2.000","Ea","Pull Box 12 x 12 Inches - Sd2.031","811.31" "2.000","Ea","Telephone Pull Box","811.32" "1.000","Ls","Traffic Control Signal Removed And Stacked","816.80" "1.000","Ls","Temporary Traffic Control Signal","816.81" "323.000","Sf","Roadside Guide Sign (g) - Aluminum Panel (Type b)","829." "400.000","Sf","Warning-Regulatory And Route Marker - Aluminum Panel (Type a)","832." "37.000","Ea","Delineation For Guard Rail Termini","833.7" "4.000","Ea","Supports For Guide Sign (d6 With d8 - Special Design) Steel","841.7" "1.000","Ls","Supports For Guide Sign (g1) Steel","844.101" "1.000","Ls","Supports For Guide Sign (g2) Steel","844.102" "1.000","Ls","Supports For Guide Sign (g3) Steel","844.103" "1.000","Ls","Supports For Guide Sign (g4) Steel","844.104" "75.000","Ea","Sign Sup (n/Guide)+Rte Mkr w/1 Brkway Post Assembly - Steel","847.1" "4900.000","Hr","Roadway Flagger","850.41" "140.000","Day","Traffic Cones For Traffic Management","851.1" "740.000","Sf","Safety Signing For Traffic Management","852." "3.000","Ea","Portable Breakaway Barricade Type Iii","853.1" "1300.000","Ft","Temporary Barrier (Tl-2)","853.2" "3700.000","Ft","Temporary Barrier Removed And Reset","853.21" "7.000","Ea","Temporary Impact Attenuator For Shoulder, Capable Of Redirection","853.42" "20.000","Ea","Temporary Impact Attenuator For Shoulder, Capable Of Redirection, Removed And Reset","853.421" "37000.000","Ft","Temporary Paving Markings - 6 Inch (Painted)","854.016" "4400.000","Ft","Temporary Paving Markings - 6 Inch (Tape)","854.036" "300.000","Day","Portable Changeable Message Sign","856.12" "89000.000","Day","Reflectorized Drum","859." "42000.000","Ft","6 Inch Reflectorized White Line (Painted)","860.106" "50.000","Ft","12 Inch Reflectorized White Line (Painted)","860.112" "37000.000","Ft","6 Inch Reflectorized Yellow Line (Painted)","861.106" "100.000","Ft","12 Inch Reflectorized Yellow Line (Painted)","861.112" "280.000","Sf","Pavement Arrows And Legends Refl. White (Thermoplastic)","864.04" "30.000","Ea","Slotted Pavement Marker One-Way Yellow","864.32" "900.000","Ea","Slotted Pavement Marker Two-Way Yellow/Yellow","864.35" "28.000","Ea","Street Name Sign","874." "4.000","Ea","Traffic Sign Removed And Reset","874.2" "79.000","Ea","Traffic Sign Removed And Stacked","874.4" "520.000","Cy","4000 Psi, 1.5 Inch, 565 Cement Concrete","901." "20.000","Cy","5000 Psi, 3/4 Inch, 685 Hp Cement Concrete","904.3" "3300.000","Lb","Steel Reinforcement For Structures","910." "18200.000","Lb","Steel Reinforcement For Structures - Epoxy Coated","910.1" "360.000","Ft","Metal Bridge Railing (3 Rail), Steel (Type s3-Tl4)","975.1" "1300.000","Ton","Modified Rockfill","986." |
||||||
Details |
|
||||||
Bidder's List | View project details and contacts | ||||||
Prospective Bidders | View project details and contacts | ||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |