Project Title | Heye Meyer Substation Upgrade |
Physical Address | View project details and contacts |
City, State (County) | Battle Ground, WA 98604 (Clark County) |
Category(s) | Heavy and Highway, Industrial/Manufacturing |
Sub-Category(s) | Power Plant, Site Development |
Contracting Method | Bids by Invitation, Competitive Bids |
Project Status | Results, Construction start expected May 2023 |
Bids Due | View project details and contacts |
Estimated Value | $982,340 [brand] Estimate |
Plans Available from | County Agency |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | The project includes the following work: Removal and disposal of the existing 115kV station equipment, structures, bus work, foundations, conduit, as well as sections of fencing, ground wire and landscaping. Station fencing will be expanded to the east and south. New 115kV station equipment will consist of a 4-breaker ring bus with three transmission lines and one transformer. Work completed on the 12kV side of the station will consist of the removal of the existing control enclosure exterior, expansion of and modification to the existing foundation, oversite of the new control enclosure installation, and installation of new panels with associated wiring. Existing equipment, panels, and wire way will remain in place during demolition and installation of the new control enclosure. Contractor will perform construction as shown in the attached drawings and in accordance with the bid documents and Summary of Work. Portions of construction will occur on existing wetlands while some wetlands on the property will remain undisturbed. Subcontractors List: A Subcontractors List must be submitted as required in the Instructions to Bidders. Questions: Questions about this project should be directed to the following individual. Depending on the nature of the question, the Utility may require the Bidder to put a question in writing. Contact Person, Title: Cathy Wannamaker, Materials Manager Phone Number: 360-992-8834 E-mail Address: cwannamaker@clarkpud.com |
||||||||||||||||||||||||||||||||||||||||||||||
Details |
|
||||||||||||||||||||||||||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |