Reported | 06/23/2022 08:36 AM |
Project Title | South Phase - Gantzel Road Phase Ii Extension:Combs To Queen Creek Wash - Cp0518 - City Of Mesa |
Physical Address | View project details and contacts |
City, State (County) | Mesa, AZ 85201 (Maricopa County) |
Category(s) | Sewer and Water |
Sub-Category(s) | Water Lines |
Contracting Method | Competitive Bids. |
Project Status | Conceptual Design, Construction Start Expected March 2024 |
Bids Due | View project details and contacts |
Estimated Value | $1,179,899 [brand] Estimate |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Increase the ability of the existing Gantzel Gate Station to feed the northern half of the Magma System. This first phase of the project will increase the flow capacity of the high pressure system north on Gantzel to the Queen Creek Wash. This project is included in the city's 2023-2027 Capital Improvement Plan (CIP). As of June 22, 2022, further details regarding design and construction have not been identified. *Project information has been obtained through a public capital improvement plan (CIP). A CIP is a financial schedule for short- and long-range projects which is updated regularly. Information listed in the CIP often evolves based on funding availability and the project details, including timeline and value, are subject to change. The content management team will continue to pursue additional details as they become available. |
||
Details |
|
||
Bidder's List | View project details and contacts | ||
Prospective Bidders | View project details and contacts | ||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |