Similar Projects
Last Updated | 08/23/2022 04:03 AM |
Project Title | City of Stephenville Eastside Sewer Interceptor - Phase 1 |
Physical Address | View project details and contacts |
City, State (County) | Stephenville, TX 76401 (Erath County) |
Category(s) | Heavy and Highway, Sewer and Water |
Sub-Category(s) | Site Development, Water Lines |
Contracting Method | Competitive Bids |
Project Status | Construction start expected September 2022 |
Bids Due | View project details and contacts |
Estimated Value | $1,560,000 [brand] Estimate |
Plans Available from | Civil Engineer |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Potential MBE Participation Goal 19.44% Potential WBE Participation Goal 9.17% The Project is located in the City of Stephenville, Texas, and consists of the following approximate quantities: City of Stephenville Stephenville, Texas Eastside Sewer Interceptor-Phase I Cost may vary. 95 Linear Feet of 4-inch SDR 26 Sewer Pipe 695 Linear Feet of 18-inch SDR 26 Sewer Pipe 944 Linear Feet of 36-inch SDR 26 Sewer Pipe 2,750 Linear Feet of 30-inch FRP Sewer Pipe 10,360 Linear Feet of 36-inch FRP Sewer Pipe 1,420 Linear Feet of 48-inch FRP Sewer Pipe This Project also consists of the installation of manholes at various depths, steel casing, and all other appurtenances as seen in the corresponding Bid Tab and Plan Set. 2. One set of paper copies for a non-refundable deposit of $50.00. Bids must be accompanied by Bid security, payable to Owner, 5 percent of Bidder's maximum Bid price (determined by adding base bid and all alternates), and by certified check, bank money order, or Bid bond. See Section 00 21 13, "Instructions to Bidders," for additional details. Awarded Bidder will be expected to furnish a Performance bond and Payment bond within 15 days after the Notice of Award is issued by Owner or its representatives. Award of this Project is contingent upon release of funds from the Texas Water Development Board (TWDB). Any Contract or Contracts awarded under this Advertisement for Bids are expected to be funded in part by a loan from TWDB. Neither the State of Texas nor any of its departments, agencies, or employees are or will be a party to this Advertisement for Bids or any resulting contracts. 00 11 13 1 All Contractors and subcontractors must comply with Davis-Bacon wage requirements. All laborers and mechanics employed by Contractors and subcontractors on this Project shall be paid wages at rates not less than the prevailing wage rates identified for this Project. All Contracts and subcontracts shall incorporate the standard Davis-Bacon Contract clauses. Wages to be paid on this Project will be governed by the Department of Labor Wage General Decision or Decisions included in the Bid documents for this Project. 04/22 Any Contract(s) awarded under this Advertisement for Bids is/are subject to the American Iron and Steel (AIS) requirements of Section 608 of the Federal Water Pollution Control Act. 01096318 This Contract is subject to the Environmental Protection Agency's (EPA) Disadvantaged Business Enterprise (DBE) Program, which includes EPA-approved fair share goals toward procurement of Minority and Women-owned Business Enterprise (M/WBE) businesses. EPA rules require that applicants and prime Contractors make a good faith effort to award a fair share of Contracts, subcontracts, and procurements to M/WBEs through demonstration of the 6 affirmative steps. Equal Opportunity in Employment - All qualified applicants will receive consideration for employment without regard to race, color, religion, sex (including pregnancy), sexual orientation, gender identity, national origin, age (40 or older), disability, or genetic information. Bidders on this Work will be required to comply with the Department of Labor regulations at 41 CFR Part 60-4, relating to Construction Contractors--Affirmative Action Requirements, which include the President's Executive Order No. 11246, as amended by Executive Order No. 11375 and Executive Order No. 13672, in the award and administration of contracts awarded under TWDB financial assistance agreements. Failure by Contractor to carry out these requirements is a material breach, which may result in the termination of the awarded financial assistance. All Contractors/subcontractors that are debarred, suspended or otherwise excluded from or ineligible for participation on federal assistance programs may not undertake any activity in part or in full under this project. City reserves the right to reject any or all bids and accept or reject any informalities. Bids may be held by the City for a period not to exceed 60 days from the date of the Bid opening for the purpose of reviewing the Bids and investigating the Bidders' qualifications prior to the Contract award. |
||
Details |
|
||
Bidder's List | View project details and contacts | ||
Prospective Bidders | View project details and contacts | ||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |