Reported | 06/28/2022 11:16 AM |
Project Title | Mad River Pipeline Valve Replacement - City of Eureka |
Physical Address | View project details and contacts |
City, State (County) | Eureka, CA (Humboldt County) |
Category(s) | Sewer and Water |
Sub-Category(s) | Water Lines |
Contracting Method | Competitive Bids. |
Project Status | Conceptual Design, Construction Start Expected March 2025 |
Bids Due | View project details and contacts |
Estimated Value | $400,000 |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Site work for a water / sewer project in Eureka, California. Conceptual plans call for site work for a water / sewer project. A series of valves on the Mad River Pipeline, the main water transmission line to the Greater Eureka Area, have been found to not operate fully. The valves in question do not close fully creating operational difficulties as well as major issues when emergency repairs are needed on the main. This project will replace the faulty valves to restore operational and emergency functionality. This Project is in included in the City of Eureka 2022-2027 Capital Improvement Plan (CIP). As of June 27, 2022, further details regarding design and construction have not been identified. *Project information has been obtained through a public capital improvement plan (CIP). A CIP is a financial schedule for short- and long-range projects which is updated regularly. Information listed in the CIP often evolves based on funding availability and the project details, including timeline and value, are subject to change. The content management team will continue to pursue additional details as they become available. |
||
Details |
|
||
Bidder's List | View project details and contacts | ||
Prospective Bidders | View project details and contacts | ||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |