Similar Projects
Last Updated | 10/13/2021 07:40 AM |
Project Title | Ocean Outfall Legislaton Program, Construction Package ST-2A, Headworks 3, Oxygenation Trains 9 and 10, and Substaton 57/58 |
Physical Address | View project details and contacts |
City, State (County) | Miami, FL 33170 (Miami-Dade County) |
Category(s) | Sewer and Water |
Sub-Category(s) | Sewage Treatment Plant |
Contracting Method | Competitive Bids. |
Project Status | Results |
Bids Due | View project details and contacts |
Estimated Value | $89,800,564 |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Project consists of furnishing all materials, labor, and equipment necessary to construct and provide fully functional systems consisting of a new influent forcemain tie-in on SW 232nd Street, new influent metering valve box, a new headworks building (Headworks 3) with an attached odor control building, construction of two new oxygenation trains (Ox. Trains 9 and 10), construction of a new substation and electrical building, and the integration of these new structures with the rest of the plant. at the South District Wastewater Treatment Plant (SDWWTP), located at 8950 SW 232nd Street Miami, Florida, 33190. The scope of work includes, but is not limited to, construction of a new influent metering valve box, a new headworks building (Headworks 3) with an attached odor control building, construction of two new oxygenation trains (Oxygenation Trains 9 and 10), construction of a new electrical substation and electrical building, and the integration of these new structures with the rest of the plant. Specifically, the work includes the following: The scope of work includes, but is not limited to: 1. Demolition - Site a. Demolition of select existing piping, pavement, conduits and duct banks as indicated in the Plans 2. Construction -232nd Street Forcemain Tie-in, Influent Metering Valve Box, Headworks 3, Odor Control Building, and Process Drain Lift Station a. Construction of a connection to an existing plant 72-inch influent force main header located on SW 232nd Street. b. Construction of a new influent valve box which will regulate the flow to a new headworks building. c. Construction of a new headworks building and grit chamber (Headworks 3). d. Construction of a new lift station which will receive flow from the process drains from the new headworks. e. Construction of interconnecting piping between existing and new facilities. f. Furnishing and installation of pumps, screens, collectors, conveyors, gates, valves, and other process mechanical equipment. g. Furnishing and installation of fire alarm systems, electrical systems, SCADA system, MCCs, conduits, duct banks, control panels and lighting systems. h. Furnishing and installation of new sensors, including flowmeters, wastewater samplers and other instruments. i. Furnishing and installation of new fire suppression systems, HVAC systems, water source heat pumps (WHPs) cooling water pumps (CWPs), cooling towers (CTs), fans, air ducts and air purification systems. j. Furnishing and installation, doors, windows, skylights, and rollup doors. k. Furnishing and installation of all plumbing. l. Furnishing and installation of all appurtenances for electrical and control room. 3. Construction - Substation 57/58 a. Construction of Substation 57/58 to power all new process areas that are part of the Work. b. Furnishing and installation of new fire alarm system, electrical systems, SCADA system, transformers, switchgears, MCCs, conduits, duct banks, control panels and lighting systems. c. Furnishing and installation of new HVAC systems, water source heat pumps (WHPs), cooling water pumps (CWPs), cooling towers (CTs), fans, air ducts and air purification system. d. Furnishing and installation, doors, windows and rollup doors. e. Furnishing and installation of all plumbing. f. Furnishing and installation of all appurtenances for control room. 4. Construction - Ox. Trains 9 and 10 and Sampling Building a. Construction of two (2) new Oxygenation Trains and Sampling Building. b. Construction of interconnecting piping between existing and new facilities. c. Furnishing and installation of new mechanical aerators, blowers, pumps, gates, valves, and other process mechanical equipment. d. Furnishing and installation of new exterior lighting systems. |
||||||||||||||||||||||||||||||||||||||||||
Details | Sewage Treatment Plant, New Construction.
|
||||||||||||||||||||||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |