Reported | 07/16/2022 12:00 AM |
Project Title | Modular Building Project |
Physical Address | View project details and contacts |
City, State (County) | San Jose, CA 95124 (Santa Clara County) |
Category(s) | Education |
Sub-Category(s) | Elementary School, Middle/Senior High School |
Contracting Method | Design-Build. Competitive Bids. |
Project Status | Accepting Qualifications, Construction Start Expected September 2022 |
Bids Due | View project details and contacts |
Estimated Value | $10,000,000 |
Plans Available from | Construction Manager |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | For the design, construction, and DSA certification of the Increment 2 Permanent Modular Building Project ("Project") at the following four (4) school sites: (a) Price Middle School, 2650 New Jersey Avenue, San Jose, CA 95124; (b) Fammatre Elementary School, 2800 New Jersey Avenue, San Jose, CA 95124; (c) Farnham Elementary School, 15711 Woodard Road, San Jose, CA 95124; and (d) Sartorette Elementary School, 3850 Woodford Drive, San Jose, CA 95124 (individually referred to as a "School Site" or collectively as the "School Sites.". Project description: Increment 2 for each site. The acquisition and installation of four single story modular buildings consisting of five (5) modular classrooms each to be installed on permanent concrete foundations, one building at each of four (4) School Sites by the selected DBE as part of overall Project. The District will use the Design Build delivery method authorized by Education Code Section 17250.20 et seq. for increment 2 with a preliminary Design Build estimate of $10 million. Increment 1 construction documents will be prepared by the District's Architect, which will include all sitework, building pads, site utilities, and building low voltage systems. DBE shall coordinate creation of the increment 2 modular building documents in collaboration with the District's Architect. The increment 1 work will be performed by sealed bid contractors separate from the DBE contract for increment 2. |
||||||||||||||||||||||||||||||||||||||||
Details | Elementary School, 1 Story Above Grade, New Construction, Middle/Senior High School, 1 Story Above Grade, New Construction.
|
||||||||||||||||||||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |