Similar Projects
Last Updated | 08/18/2022 05:31 AM |
Project Title | Professional Boulevard Phase II |
Physical Address | View project details and contacts |
City, State (County) | Hagerstown, MD 21742 (Washington County) |
Category(s) | Heavy and Highway, Outdoor Lighting, Sewer and Water |
Sub-Category(s) | Maintenance, Paving/Reconstruction, Roadway Lighting, Sidewalks/Parking Lot, Site Development, Water Lines |
Contracting Method | Competitive Bids |
Project Status | Construction start expected August 2022 |
Bids Due | View project details and contacts |
Estimated Value | $6,617,402 [brand] Estimate |
Plans Available from | Agency's Affiliate |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | As of August 17, 2022, project was awarded to Concrete General, Inc., awarded amount is $6,617,402.10. Project No: 10-270 Continuing from previous phases to widen 1100 feet of existing Professional Court from 2 to 4 lanes including utility and storm drain improvements and signal upgrades to the intersection with Eastern Boulevard. Existing roadway lighting will be moved and updated as well as lighting installation across the newly constructed bridge. Roadway paving will extend from the bridge 2400 feet to a prior built stub off the Yale Drive roundabout. Bioswales and Filterra inlets will be constructed to treat the stormwater. A shared use path and sidewalk system will run the entire length of the project and traffic barrier is included with the design. Questions due: Friday, July 1, 2022, by 4:00 PM (Written inquires regarding this bid should be submitted via Fax (240-313-2401) to the attention of Blair Reynolds, Project Manager, or by email to ecbidquestions@washco-md.net.) To commence work as specified in the Notice to Proceed and to prosecute the work to complete the contract within/or before 350 (Calendar Days) The Contractor is hereby advised that liquidated damages in the amount of $500 dollars per calendar day will be assessed for unauthorized extensions beyond the contracted time of completion. A bid security totaling at least five percent (5%) of the bid amount will be required on contracts of $100,000 or over When the Contractor bid is $100,000 or more, the Contractor shall furnish a Payment Bond and a Performance Bond in the full amount of the Contract Award as security for the construction and completion of the contract in conformance with the Plans, Standard Specifications, revisions thereto, General Provisions and Special Provisions |
||||||||||
Details |
|
||||||||||
Bidder's List | View project details and contacts | ||||||||||
Prospective Bidders | View project details and contacts | ||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |